YERINGTON, Nev., Nov. 03, 2022 (GLOBE NEWSWIRE) — Nevada Copper (TSX: NCU) (OTC: NEVDF) (FSE: ZYTA) (“Nevada Copper” or the “Company”) is pleased to provide an update on restart and operational activities for its underground mine (the “Underground Mine”) following the closing of the restart financing package that provides up to US$123 million of liquidity to the Company, as announced in the Company’s October 28, 2022 press release.
Additionally, the Company announces the addition to its Board of Directors of Guillaume de Dardel, Head of Energy Transition Metals and part of the Energy Transition desk at Mercuria Energy Trading SA (“Mercuria”), one of Nevada Copper’s largest shareholders.
Operational Updates
Optimized Mine Plan – John Wood Group plc, has completed an optimized life-of-mine plan that focuses on accessing the larger, higher-grade stopes of the East North Zone (“EN Zone”) to bring value forward in the mine life. This optimized plan is being incorporated into our development and mine planning in preparation for restart of mining operations.
Final Dike Crossings – As indicated in the Company’s October 5, 2022 press release, the Company continues to build on the significant progress made to date with the completion of the second dike crossing. This critical achievement provides access to the higher-grade stopes of the EN Zone that is estimated to represent the highest value area of the underground reserve. This zone also represents the most competent geotechnical rock mass within the reserve which is expected to allow larger stopes to be extracted, significantly improving production efficiencies. The Company is encouraged by the rock quality being encountered beyond the dike as progress is made on development headings into the EN Zone, and appears to be as predicted by the geotechnical models. To date, nine of the first stopes to be mined have been drilled to provide critical data for final stope design in preparation for the commencement of mining in the second half of 2023.
The underground crews have transitioned to work on the final dike crossing which is expected to be completed in early 2023. A well-known industry grouting and geotechnical consultant has been engaged in developing the final dike crossing design and plan. The completion of the dike crossing will provide necessary access for a development contractor to begin rapid development into the EN Zone in early 2023.
Development Contractor – The Company has received indications of interest in providing proposals for development mining from six large, well-known, and established mining contractors. Discussions are in the advanced stages with these contractors and the Company expects to award a contract by the end of 2022.
Capital Projects Proceeding – The Company has signed a letter of intent (“LOI”) with an engineering firm to bring critical capital projects to completion, including the coarse ore bin, permanent dewatering system, vent shaft rehabilitation and surface fans. The scope of the LOI includes delivery of construction execution plans within the next 30 days. These execution plans would identify any procurement or fabrication of materials and equipment to complete the construction activities, labor requirements, and necessary activities ancillary to these capital projects.
The Company has also secured the remaining long-lead item for the coarse ore bin project, the underground jaw crusher, which is expected to be delivered in November 2022.
Strengthening the Site Technical Leadership – The operations leadership has been strengthened with the recent additions of highly experienced individuals in critical technical and operational roles. Included in these recent additions are an Underground Mine Manager, a Capital Projects Manager, a Senior Paste Backfill Engineer, a Contracts Manager, and a Senior Geotechnical Engineer. The Company has also started to fill out the underground operations crews with several skilled mining and operations crews that will focus on capital development projects ahead of stope mining that is planned to begin in the second half of 2023.
Board Addition
Guillaume de Dardel, Head of Energy Transition Metals and part of the Energy Transition desk at Mercuria, will join the Board of Directors of the Company effective November 4, 2022. Mercuria is a significant shareholder in Nevada Copper. Mr. de Dardel studied in Sao Paulo and Switzerland and holds a BA HSG (magna cum laude) from the University of St. Gallen.
Mercuria is one of the world’s largest independent global energy and commodities groups and makes strategic investments to provide access to key infrastructure and physical commodity markets. They have expanded rapidly into renewables and the energy transition which has become a core pillar of Mercuria’s strategy.
Qualified Person
The technical information and data in this news release has been reviewed by Steven Newman, Registered Member – SME, Vice President, Technical Services for Nevada Copper, who is a non-independent Qualified Person within the meaning of NI 43-101.
About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
Randy Buffington President & CEO
For additional information, please see the Company’s website at www.nevadacopper.com, or contact:
Tracey Thom | Vice President, IR and Community Relations tthom@nevadacopper.com +1 775 391 9029
Cautionary Language on Forward Looking Statements This news release contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts, are forward-looking statements. Such forward-looking information and forward-looking statements specifically include, but are not limited to, statements that relate to the development plans for the Underground Mine and the expected results thereof.
Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Such risks and uncertainties include, without limitation, those relating to: requirements for additional capital and no assurance can be given regarding the availability thereof; the outcome of discussions with creditors and vendors; the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; the impact of COVID-19 on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rate increases; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labour disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; dependence on management information systems and cyber security risks; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022. The forward-looking statements and information contained in this news release are based upon assumptions management believes to be reasonable, including, without limitation: no adverse developments in respect of the property or operations at the project; no material changes to applicable laws; the ramp-up of operations at the Underground Mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of COVID-19 going forward; the Company will be able to obtain sufficient additional funding to complete the ramp-up, no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended.
The forward-looking information and statements are stated as of the date hereof. The Company disclaims any intent or obligation to update forward-looking statements or information except as required by law. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking information and statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. Specific reference is made to “Risk Factors” in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022, for a discussion of factors that may affect forward-looking statements and information. Should one or more of these risks or uncertainties materialize, should other risks or uncertainties materialize or should underlying assumptions prove incorrect, actual results and events may vary materially from those described in forward-looking statements and information. For more information on the Company and the risks and challenges of its business, investors should review the Company’s filings that are available at www.sedar.com.
The Company provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.
YERINGTON, Nev., Sept. 26, 2022 (GLOBE NEWSWIRE) — Nevada Copper (TSX: NCU) (OTC: NEVDF) (FSE: ZYTA) (“Nevada Copper” or the “Company”) is pleased to provide an update on planned restart activities at its Pumpkin Hollow underground copper mine (the “Underground Mine”) and developments with respect to the proposed financing package that was previously announced in the Company’s news release dated August 25, 2022 (the “Prior Announcement”). The financing is expected to provide up to US$93 million of liquidity to the Company in order to support the restart and ramp-up of the Underground Mine (the “Restart Financing Package”).
Randy Buffington, President & CEO, commented: “These past few weeks the team has been focused on ensuring that we are prepared for the restart of underground operations. We have made significant progress in developing the plans, recruiting the people and implementing the systems necessary to derisk the restart. We have attracted several key technical positions and built the initial underground team to be able to execute on the first critical projects, primarily the remaining two dike crossings required to access the EN zone. We believe that taking a careful, phased approach to restarting the mine removes some of the bottlenecks the operation has faced in the past and will facilitate a rapid ramp-up to nameplate capacity once the mill restarts in mid-2023. We are looking forward to completing the capital projects and bringing the underground mine up to full operations so that we can turn our attention to development of the large open pit project. I continue to appreciate the ongoing commitment and support of our team and key stakeholders as we work diligently to close this financing and get back to operations.”
Operations and Mine Planning Activities Update
As previously announced, the Company has advanced planning for the restart of operations at its Underground Mine. The Company engaged a third-party consulting firm, John Wood Group plc, to complete a mine plan focusing on accessing the larger, higher-grade stopes in the East North Zone (EN Zone). The mine plan has been completed with an optimized stoping sequence that brings value forward in the life of mine and derisks the restart by advancing development activities and building significant underground inventory ahead of restarting the mill in mid-2023. Included in the mine plan are updated operating costs, which are not expected to be materially different from previous estimates as they have not been significantly impacted by inflationary pressures.
The restart plan, as envisaged, will be executed in three phases following the closing of the Restart Financing Package:
Phase 1 – Completion of the remaining two dike crossings and certain capital projects, workforce development
Phase 2 – Underground stope and inventory development
Phase 3 – Stope mining and mill start-up
In September, the Company entered Phase 1 by reinitiating development activities with one mining crew focused on completing the second dike crossing. It is anticipated that the crossing will be completed and well advanced beyond the geological dike feature within the next 30 days, at which time the crew will move onto the third and final dike crossing. In addition, the Company is preparing to issue bid packages to interested development contractors to perform underground development activities and for completion of the remaining capital projects, including: (i) coarse ore bin 2; (ii) vent shaft stripping and surface fans installation; and (iii) Geho dewatering system.
In early 2023, the Company plans to begin rapid development with the use of a development contractor to advance into the higher-grade stopes of the EN Zone and build significant underground ore inventory. The Company will continue to recruit additional underground personnel to prepare for stope mining in the second quarter of 2023. With a significant stockpile of ore on surface and underground inventory expected to be built up, the mill is planned to start up in the third quarter of 2023.
Restart Financing Package Update
As disclosed in the Prior Announcement, the key components of the Restart Financing Package are as follows:
Equity Investments (US$40 million): Pala Investments Limited (“Pala”), the Company’s largest shareholder, and Mercuria Energy (“Mercuria”), a significant shareholder of the Company, are each expected to provide US$20 million in exchange for common shares of the Company (“Common Shares”). Pala has already advanced US$13.5 million of such funding to the Company.
Stream and Royalty Financing (US$30 million): Triple Flag Precious Metals Corp. (“Triple Flag”) is expected to increase its existing net smelter returns royalty on the Company’s open pit project from 0.7% to 2% for a purchase price of approximately US$26.2 million, subject to a full buyback of the increased royalty percentage. In addition, Triple Flag is expected to accelerate the approximately US$3.8 million remaining to be funded under the Company’s existing metals purchase and sale agreement with Triple Flag.
KfW Facility Extension (US$15 million committed): The Company’s senior credit facility (the “KfW Facility”) with KfW IPEX-Bank GmbH (“KfW”) is expected to be amended to provide for a new tranche of up to US$25 million, of which Pala, Triple Flag and Mercuria would commit the first US$15 million as a backstop.
Deferrals under Senior Project Facility and Working Capital Facility (expected to be at least US$8 million): KfW is expected to defer three interest payments under the KfW Facility. Concord Resources Limited is expected to defer interest and principal payments under the Company’s working capital facility.
Under the Restart Financing Package, Pala is expected to consolidate approximately US$73 million of the indebtedness currently owing to Pala by the Company into an amended or new debt instrument (the “Pala Debt Instrument”), which indebtedness would be convertible into Common Shares.
Please see the Prior Announcement for additional details regarding the Restart Financing Package.
Nevada Copper reminds shareholders that the terms of the Restart Financing Package are currently non-binding and closing is subject to, among other things, finalization of the specific terms thereof, negotiation and execution of definitive documentation and the satisfaction of various regulatory requirements. The Company and its key financing partners intend to enter into definitive documents in respect of and close the Restart Financing Package concurrently on or about October 5, 2022 (the “Closing Date”). The closing of the Restart Financing Package will be subject to the approval of the Toronto Stock Exchange (the “TSX”).
As disclosed in the Prior Announcement, there can be no assurance that binding agreements will be entered into or completed (or the required regulatory approvals obtained) on terms satisfactory to the Company and within the required timeframe, or at all. In addition, there can be no assurance that the Company will be able to raise the further funding to supplement the Restart Financing Package that will be required to complete the restart and ramp-up process. The Company expects the costs of the restart and ramp-up process to be in the range of US$70 million-US$75 million. In addition, the Company needs to satisfy and/or defer various outstanding vendor payables. Together these costs and payables are expected to exceed the amount of the Restart Financing Package. As a result, the Company continues to evaluate other additional financing options, including a public offering.
The Company intends to use the available proceeds from the Restart Financing Package of approximately US$71.5 million (representing the US$93 million of liquidity less US$13.5 million already advanced by Pala and less US$8 million in deferrals under the KfW Facility and the Company’s working capital facility) to fund ramp-up costs (approximately US$15.7 million to fund capital expenditures and approximately US$29.1 million to fund operating costs), vendor payments (approximately US$23.5 million) and for general corporate purposes, such as overhead (approximately US$3.2 million).
If the Restart Financing Package is not completed, absent other financing, the Company will not be able to continue carrying on business in the ordinary course and may need to pursue proceedings for creditor protection. The Company’s creditors may also seek to commence enforcement action, including realizing on their security over the Company’s assets.
Potential Maximum Dilution in Respect of the Restart Financing Package
Pala currently owns 167,759,110 Common Shares, representing approximately 37% of the outstanding Common Shares on a non-diluted basis. Mercuria currently owns 48,700,000 Common Shares, representing approximately 11% of the outstanding Common Shares on a non-diluted basis.
Pala is expected to fund its equity investment of US$20 million by the cancellation of approximately US$13.5 million in short-term debt advanced to the Company by Pala as interim financing and by the payment of approximately US$6.5 million on the Closing Date. The Pala Equity Investment will be at a subscription price equal to a 15% discount to the five-day volume weighted average price (the “VWAP”) of the Common Shares on the TSX as of the trading day prior to the Closing Date (the “Equity Subscription Price”). By way of illustration, if the closing of the Pala Equity Investment occurred on September 23, 2022, 120,088,496 Common Shares would be issued to Pala using a 15% discount to the five-day VWAP of C$0.266 and then converting such VWAP into U.S. dollars using the Bank of Canada exchange rate on September 23, 2022 of C$1.00=US$0.7369 (the “Illustrative Equity Subscription Price”). In addition, approximately US$1.665 million of guarantee and other fees will be satisfied by the issuance of Common Shares to Pala at the Equity Subscription Price. Based on the Illustrative Equity Subscription Price, this will result in an additional 9,999,655 Common Shares being issued to Pala. The transactions described in this paragraph together with the Pala Debt Instrument are referred to as the “Pala Equity Investment” herein.
Mercuria is expected to fund its equity investment of US$20 million in two tranches. The first tranche of US$10 million will be paid on the Closing Date. The second tranche of US$10 million will be deposited into escrow on the Closing Date and will be released upon the satisfaction or waiver of certain conditions. These conditions include the completion of certain steps in the ramp-up process that the Company expects to achieve before the end of 2022. The first tranche of the Mercuria Equity Investment will be at a subscription price equal to the Equity Subscription Price. The second tranche of the Mercuria Equity Investment will be at a subscription price equal to a 15% discount to the five-day VWAP of the Common Shares on the TSX as of the trading day prior to the applicable date of closing. By way of illustration, if the closing of both tranches of the Mercuria Equity Investment occurred today, 120,088,496 Common Shares would be issued to Mercuria using the Illustrative Equity Subscription Price.
In connection with the Mercuria Equity Investment, Mercuria is expected to receive Common Share purchase warrants of the Company (the “Warrants”). Each Warrant will entitle Mercuria to, subject to satisfying certain vesting conditions, acquire one Common Share at an exercise price equal to a 20% premium to the Equity Subscription Price. The Warrants will vest, from time to time, in conjunction with the conversion of the Pala Debt Instrument, thereby providing Mercuria with an ability to maintain its pro rata shareholding interest. The vesting of 50% of the Warrants will also be subject to the vesting condition that the second tranche of the Mercuria Equity Investment has closed. The Warrants will expire upon maturity of the Pala Debt Instrument. By way of illustration, if all Warrants vested and were exercised today, 119,205,651 Common Shares would be issued to Mercuria assuming the illustrated conversion of the Pala Debt Instrument described below. The transactions described in the foregoing two paragraphs are referred to as the “Mercuria Equity Investment” herein (the Mercuria Equity Investment together with the Pala Equity Investment are referred to herein as the “Equity Investments”).
Pala is expected to consolidate approximately US$73 million of the indebtedness currently owing to Pala by the Company into the Pala Debt Instrument. The loans outstanding to be consolidated into the Pala Debt Instrument would include (i) the total of approximately US$53 million outstanding under the existing credit agreement entered into by Pala and the Company in November 2021; and (ii) US$20 million that was advanced to the Company under a promissory note in June and July 2022. In connection with the entering of the Pala Debt Instrument, a 4% fee on the US$20 million amount referred to above will be payable to Pala and capitalized as additional principal under the Pala Debt Instrument. Amounts owing under the Pala Debt Instrument would be convertible into Common Shares, at Pala’s option, at a conversion price equal to a 20% premium to the Equity Subscription Price. By way of illustration, if all amounts owing under the Pala Debt Instrument were converted today, 374,402,808 Common Shares would be issued to Pala using a 20% premium to the Illustrative Equity Subscription Price.
Based on the above illustrations, the number of Common Shares that will be issued as a result of the Equity Investments is set out below, assuming the conversion in full of the Pala Debt Instrument and the exercise in full of the Warrants:
Total Number of Common Shares currently held
Total Number of Common Shares that will be held after the Equity Investments excluding conversion of the Pala Debt Instrument and exercise of the Warrants
Total Number of Common Shares that will be held after the Equity Investments including conversion of the Pala Debt Instrument and exercise of the Warrants
% of Common Shares currently owned relative to Common Shares currently outstanding
% of Common Shares owned relative to Common Shares outstanding after the Equity Investments excluding conversion of the Pala Debt Instrument and exercise of the Warrants
% of Common Shares owned relative to Common Shares outstanding after the Equity Investments including conversion of the Pala Debt Instrument and exercise of the Warrants
Pala
167,759,110
297,847,261
672,250,069
37.41%
42.63%
56.39%
Mercuria
48,700,000
168,788,496
287,994,147
10.86%
24.16%
24.16%
The total number of Common Shares to be issued pursuant to the Equity Investments (excluding conversion of the Pala Debt Instrument and exercise of the Warrants) is 250,176,647, which represents approximately 56% relative to the number of Common Shares currently issued and outstanding. The total number of Common Shares to be issued pursuant to the Equity Investments (including conversion of the Pala Debt Instrument and exercise of the Warrants) is 743,785,105, which represents approximately 166% relative to the number of Common Shares currently issued and outstanding.
TSX Financial Hardship Exemption
Nevada Copper has applied to the TSX, pursuant to the provisions of Section 604(e) of the TSX Company Manual, for a “financial hardship” exemption from the requirements to obtain shareholder approval of components of the Restart Financing Package on the basis that, absent the Restart Financing Package the Company is in serious financial difficulty due to the lack of available cash and funding resources. Moreover, the Company is currently in default under its various credit facilities and the Company’s metals purchase and sale agreement with Triple Flag. The Restart Financing Package, including the Equity Investments, are designed to improve the Company’s financial situation. The entry into of each of the definitive agreements required in respect of the Restart Financing Package will occur concurrently. The application was approved by the Special Committee (as defined below) who has determined that the transactions discussed herein are reasonable for Nevada Copper in the circumstances. Under the policies of the TSX, on the basis that the Restart Financing Package was determined to be subject to the provisions of Section 607 of the TSX Company Manual for private placements, components of the Restart Financing Package would have required shareholder approval by the Company due to: (a) the number of Common Shares (including the Common Shares issuable upon the conversion of the Pala Debt Instrument and upon exercise of the Warrants) issuable in connection with the Restart Financing Package is in excess of 25% of the number of Common Shares outstanding; (b) the number of Common Shares to be issued to insiders (assuming conversion of the Pala Debt Instrument and exercise Warrants) is greater than 10% of the number of Common Shares outstanding; and (c) the consideration (being the Equity Investments) to be received by insiders is greater than 10% of the Company’s market capitalization. The Restart Financing Package will not materially affect control of the Company given Pala’s existing level of ownership in the Company.
The board of directors of the Company (the “Board”) has formed a special committee (the “Special Committee”) consisting of members of the Board who are independent of Pala, Mercuria and management of the Company, to consider the proposed terms of the Restart Financing Package, including the terms of the Equity Investments. The Special Committee has meet continuously throughout the negotiation of the proposed terms of the Restart Financing Package.
Nevada Copper expects that as a consequence of its financial hardship application, the TSX will conduct a remedial delisting review of the Company. Although Nevada Copper believes that it will be in compliance with all continued listing requirements of the TSX upon the closing of the Restart Financing Package, no assurance can be provided as to the outcome of such review or continued qualification for listing on the TSX. There can be no assurance that the TSX will accept the application for the use of the financial hardship exemption from the requirement to obtain shareholder approval described above.
The Equity Investments will be related party transactions of the Company for purposes of Multilateral Instrument 61-101 – Protection of Minority Security Holders in Special Transactions (“MI 61-101”) and are subject to the formal valuation and minority approval requirements thereof, unless an exemption is available. It is the intention of the Company to rely on the financial hardship exemption provided for in Sections 5.5(g) and 5.7(e) of MI 61-101.
Qualified Person
The technical information and data in this news release has been reviewed by Steven Newman, Registered Member – SME, Vice President, Technical Services for Nevada Copper, who is a non-independent Qualified Person within the meaning of NI 43-101.
About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
Randy Buffington President & CEO
For additional information, please see the Company’s website at www.nevadacopper.com, or contact:
Tracey Thom | Vice President, IR and Community Relations tthom@nevadacopper.com +1 775 391 9029
Cautionary Language on Forward Looking Statements This news release contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts, are forward-looking statements. Such forward-looking information and forward-looking statements specifically include, but are not limited to, statements that relate to the completion of the funding package described above, including the terms and timing thereof, the plans and requirement for supplementary financing and the expected amounts thereof, regulatory requirements, the Company’s “financial hardship” exemption application, the use of proceeds from the Restart Financing Package, creditor protection proceedings, mine planning, the execution of the mine restart plan and expected development schedule, and the expected costs of the restart and ramp-up process. There can be no assurance that the Restart Financing Package will close or that the cost estimates or allocation thereof will be accurate.
Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Such risks and uncertainties include, without limitation, those relating to: requirements for additional capital and no assurance can be given regarding the availability thereof; the outcome of discussions with creditors and vendors; potential creditor protection proceedings; the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; the impact of COVID-19 on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rate increases; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labour disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; dependence on management information systems and cyber security risks; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022. The forward-looking statements and information contained in this news release are based upon assumptions management believes to be reasonable, including, without limitation: no adverse developments in respect of the property or operations at the project; no material changes to applicable laws; the ramp-up of operations at the Underground Mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of COVID-19 going forward; the Company will be able to obtain sufficient additional funding to complete the ramp-up, no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended.
The forward-looking information and statements are stated as of the date hereof. The Company disclaims any intent or obligation to update forward-looking statements or information except as required by law. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking information and statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. Specific reference is made to “Risk Factors” in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022, for a discussion of factors that may affect forward-looking statements and information. Should one or more of these risks or uncertainties materialize, should other risks or uncertainties materialize or should underlying assumptions prove incorrect, actual results and events may vary materially from those described in forward-looking statements and information. For more information on the Company and the risks and challenges of its business, investors should review the Company’s filings that are available at www.sedar.com.
The Company provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.
By 2025, the metals could be priced at $15,000 a tonne (U$6.80 per pound), a rise of 66%. (current copper price is $9,300 per tonne (U$4.24 per pound)) Goldman said in a report titled “Copper is the new Oil”
The report also drills down into three drivers of green copper demand: electric vehicles (EVs); solar power and wind power. The bank estimates that 5.1 million EVs likely will be sold in 2021, rising to 31.51 million EVs in the year 2030. It also forecasts that 30 million charging units will be installed in 2030.
A rising tide of electrification, as many countries seek to lower their emissions through developing new technologies, promises robust demand for years to come. Global copper production would need to rise by between 3% and 6% per annum by 2030 for countries to meet the targets of the Paris Agreement on climate change, according to a Sept. 14 Bernstein Research note.
YERINGTON, Nev., Aug. 05, 2022 (GLOBE NEWSWIRE) — Nevada Copper (TSX: NCU) (OTC: NEVDF) (FSE: ZYTA) (“Nevada Copper” or the “Company”) provides an update on its operations and financing initiatives and activities at its Pumpkin Hollow copper mine (the “Underground Mine”) located in Yerington, Nevada.
Operational Restart Planning
During July, management has advanced its Underground Mine restart plans, which focus on the acceleration of key capital items followed by the development of a significant stope ore inventory in advance of a mill restart and completion of production ramp-up. The development of restart plans has allowed the Company to advance financing discussions with its key stakeholders. The commencement of restart activities is contingent on the Company obtaining long-term financing, as discussed below.
The Company continues to work with its creditors and vendors to defer payments and maintain the operation in a temporary suspension status, with only limited operational activities being undertaken to protect the Company’s assets, to minimize cash burn until closing of a restart funding package.
Restart Financing
The Company is engaged in active and ongoing discussions with its key financing partners with respect to a substantial funding package for the restart and ramp-up of the Underground Mine (as an alternative to the smaller financing package referred to in the Company’s July 4, 2022 press release which is no longer being pursued in that form).https://embed.fireplace.yahoo.com/embed?ctrl=Monalixa&m_id=monalixa&m_mode=document&site=sports&os=android&pageContext=%257B%2522ctopid%2522%253A%25221542500%253B1577000%2522%252C%2522hashtag%2522%253A%25221542500%253B1577000%2522%252C%2522wiki_topics%2522%253A%2522Company%253BYerington%252C_Nevada%253BBankruptcy%253BDebate%253BUnderground_hard-rock_mining%2522%252C%2522lmsid%2522%253A%2522a0770000002m0AbAAI%2522%252C%2522revsp%2522%253A%2522globenewswire.com%2522%252C%2522lpstaid%2522%253A%2522618b261d-7539-34cc-9b63-9cf83c3f5fd6%2522%252C%2522pageContentType%2522%253A%2522story%2522%257D
The Company has expended the full amount of the previously disclosed US$20 million promissory note from Pala Investments Limited (“Pala”), the Company’s largest shareholder. Pala has indicated that it is prepared to provide additional financing of up to US$20 million through further promissory notes (US$4 million of which has already been advanced) while the Company continues discussions with its financing partners. The Company will continue to require interim financing until a restart funding package is secured and closed. As previously disclosed, pending completion of a financing package, the Company has not made payments due to certain creditors and vendors and is in default of its obligations under certain financing agreements and other contractual arrangements.
There can be no assurance that the Company will obtain additional interim financing or that the longer-term restart funding package will be agreed or completed on terms satisfactory to the Company and within the required timeframe, or at all. In the absence of securing such arrangements or alternative financing arrangements, the Company will not be able to continue carrying on business in the ordinary course and may need to pursue proceedings for creditor protection. The Company’s creditors may also seek to commence enforcement action, including realizing on their security over the Company’s assets.
About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
Randy Buffington President & CEO
For additional information, please see the Company’s website at www.nevadacopper.com, or contact:
Tracey Thom | Vice President, IR and Community Relations tthom@nevadacopper.com +1 775 391 9029
Cautionary Language on Forward Looking Statements This news release contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts, are forward-looking statements. Such forward-looking information and forward-looking statements specifically include, but are not limited to, statements that relate to mine planning, financing requirements, discussions with financing partners, and creditor protection proceedings.
Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Such risks and uncertainties include, without limitation, those relating to: requirements for additional capital and no assurance can be given regarding the availability thereof; the outcome of discussions with creditors and vendors; potential creditor protection proceedings; the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; the impact of COVID-19 on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labour disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; dependence on management information systems and cyber security risks; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022. The forward-looking statements and information contained in this press release are based upon assumptions management believes to be reasonable, including, without limitation: no adverse developments in respect of the property or operations at the project; no material changes to applicable laws; the ramp-up of operations at the Underground Mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of COVID-19 going forward; the Company will be able to obtain sufficient additional funding to complete the ramp-up, no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended.
The forward-looking information and statements are stated as of the date hereof. The Company disclaims any intent or obligation to update forward-looking statements or information except as required by law. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking information and statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. Specific reference is made to “Risk Factors” in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022, for a discussion of factors that may affect forward-looking statements and information. Should one or more of these risks or uncertainties materialize, should other risks or uncertainties materialize or should underlying assumptions prove incorrect, actual results and events may vary materially from those described in forward-looking statements and information. For more information on the Company and the risks and challenges of its business, investors should review the Company’s filings that are available at www.sedar.com.
The Company provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.
YERINGTON, Nev., May 16, 2022 (GLOBE NEWSWIRE) — Nevada Copper (TSX: NCU) (OTC: NEVDF) (FSE: ZYTA) (“Nevada Copper” or the “Company”) today announced its first quarter 2022 financial and operating results as well as recent milestone achievements and updates on key development initiatives for its Pumpkin Hollow underground mine (the “Underground Mine”) and open pit project (the “Open Pit Project”). The Company has filed its interim financial statements and the related management’s discussion and analysis (“MD&A”) for the quarter ended March 31, 2022 with the Canadian securities regulatory authorities, which documents can be accessed under the Company’s profile on www.SEDAR.com.
Recent Developments
Underground Mine Ramp Up Continues: Underground production continues to ramp up with hoisting rates of a combination of stope ore and development material expected to increase to approximately 3,000 tons per day (“tpd”) in Q2 2022 and then further increasing to 4,000 to 4,500 tpd during Q3 2022.
Paste Plant Commissioning: The Underground Mine paste plant began wet commissioning and filling of the first stope with paste backfill in April 2022. Paste plant commissioning activities are ongoing with initial throughput capacity expected to be realized by the end of June 2022. It is expected that the implementation of paste backfilling will result in quicker stope turnover leading to improvements in hoisting and production rates going forward.
Surface Vent Installation and Third Ore Pass Construction: The dry commissioning of the surface ventilation fans was completed in early April. Initial excavation of the third ore pass is complete with construction activities scheduled for completion in Q3 2022.
Open Pit Drill Program Commenced: The 2022/23 drill program commenced with one drill arriving on site in late April and a second drill planned to arrive during the second quarter. The primary goals of the planned approximate 25,000-foot (“ft”) drill program are upgrading in-pit inferred mineral resources that are currently considered as waste in the 2019 Technical Report1, to a minimum of an indicated resource, and expanding mineral resources previously inaccessible for drilling. Drilling will also be used to advance the geotechnical and metallurgical understanding of the deposit. Condemnation drilling will be completed in areas planned for major infrastructure. Several holes are also planned to follow up geophysical and surface work and test the nearby Tedeboy porphyry target.
Open Pit Project Prefeasibility Study (“PFS”) Update on Track: The Open Pit Project PFS update is progressing well and is expected to be completed in Q3 2022, as planned. The PFS will include updated mineral reserves and resources and economics based on current metals prices, costs, project development strategy and the contemplated solar project, which is expected to have a positive impact on the long-term price expectations for power. The results of the drill program currently underway will not be included in the PFS, however, they are expected to be included in an open pit feasibility study planned for the second half of 2023. The Open Pit Project has all the material permits required at this time for mine construction and operations and proven and probable mineral reserves, as estimated in the 2019 Technical Report, were 3,590 million pounds of copper (385.7 million tons grading 0.47% copper).
Key Team Additions: Continued strengthening of the team with the hiring of experienced individuals in the following roles: VP Technical Services; VP Human Resources; VP Finance; VP Investor Relations and Community Relations; Director Safety & Health; Director Supply Chain; Chief Reliability Engineer; Underground Production Manager; Process Manager; IT Manager; and several critical hires in Process Maintenance.
Randy Buffington, President & CEO stated, “I am very pleased with the progress we are making on several fronts at Pumpkin Hollow. We have completed a number of key projects at site that are aimed at improving productivity, stope availability and equipment reliability for the Underground Mine. The prefeasibility study update for the fully permitted Open Pit Project is well underway and will include important sustainable initiatives such as the solar project. In addition, the commencement of our exploration program is an important step towards our longer-term growth strategy. We are laying the groundwork necessary to demonstrate the potential for this significant copper operation and assembling the right team to execute on these plans for the long-term benefit of our stakeholders.”
Q1 2022 Highlights
Underground Mine Operations
Underground Mining Operations – During Q1 2022, the Company hoisted approximately 97,518 tons of material, a 66% improvement over Q4 2021. Included in the material hoisted was approximately 32,025 tons at an average grade of 1.3% copper mined from 3 stopes including ore mined from stopes in the Sugar Cube zone.
Lateral Development – Lateral development rates improved 31% in Q1 2022 compared with Q4 2021, with 3,126 ft developed. Two additional loaders were lowered underground in April 2022 further increasing mucking capacity and an additional haul truck is scheduled to be hoisted in May 2022. Ore tons mined from development during Q1 2022 were 65,493 tons, at an average grade of 0.7% copper. As previously disclosed, the Company continues to advance across a water-bearing dike structure with the first crossing being completed and grouting activities underway on the second crossing to be followed by advancing development under steel sets through the dike. While there have been some challenges due to highly variable ground and water conditions, the Company is advancing development from Ramp 01 on the other side of the dike to maintain the production schedule. The Company expects to complete the second crossing in Q2 2022.
Processing Plant – During Q1 2022, 96,414 tons of ore were processed, a 76% increase over Q4 2021. Processing plant recovery improved by 5% to 84% from Q4 2021. Copper concentrate sales increased by 50% to approximately 2,099 tons of concentrate at an average copper grade of 23%, compared to 1,403 tons of concentrate at an average copper grade of 23% in Q4 2021. The Company continued to batch process ore during Q1 2022, however the number of operating days improved by 112% from 17 days in Q4 2021 to 36 days in Q1 2022.
Q1 2022 Financial Statements and MD&A
The Company has filed on SEDAR its condensed consolidated interim financial statements and the related management’s discussion and analysis for the quarter ended March 31, 2022. These documents are available on the Company’s website at www.nevadacopper.com and the Company’s SEDAR profile at www.sedar.com.
Management Team Changes
In April 2022, Tracey Thom joined the Company as Vice President, Investor Relations and Community Relations. Tracey’s primary roles include implementing and managing the ongoing investor and community relations strategy that aligns all stakeholder engagement with the Company’s vision and goals.
Tracey brings over 25 years of senior management and investor relations experience in the mining industry and joins Nevada Copper from Hycroft Mining Holding Corporation where she was Vice President, Investor Relations and Corporate Communication for over 13 years. Prior to that she held senior executive roles in single and dually listed companies ranging from exploration and development to multi-national operations including Andina Minerals, Kinross Gold Corporation, and TVX Gold Inc.
Effective May 23, 2022, Kris Sims will assume the role of Interim Chief Financial Officer (“CFO”) following the departure of Andre van Niekerk as Executive Vice President and CFO, who is leaving for personal reasons. Kris is a seasoned financial professional with over 30 years of experience in the mining industry in executive leadership roles with large operating and development companies in the precious and base metals sectors including Phelps Dodge Mining Company, Freeport McMoRan Copper and Gold and Kinross Gold Corporation. He focuses on establishing fiscal transparency and accountability, operational excellence, profitability, and sustainability for the companies he works with. He has also been an advocate for mining in Nevada and led the Nevada Mining Association as Chairman in 2015. Kris was previously employed with Nevada Copper as Project Manager and has a strong base of institutional knowledge that will be key to moving forward and transitioning the CFO role.
“On behalf of the Board and Nevada Copper team, our sincere appreciation for the strong leadership and commitment Andre provided during his tenure,” said Randy Buffington. “He has been an incredible asset and we wish him well in his future endeavors. I am glad we are able to seamlessly integrate Kris into this leadership role as his experience and institutional knowledge will be valuable during our ongoing ramp up.”
Qualified Persons
The technical information and data in this news release has been reviewed by Greg French, C.P.G., Vice President, Exploration and Steven Newman, Registered Member – SME, Vice President, Technical Services for Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.
About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
Randy Buffington President & CEO
For additional information, please see the Company’s website at www.nevadacopper.com, or contact:
Tracey Thom | Vice President, IR and Community Relations tthom@nevadacopper.com +1 775 391 9029
____________ 1 Technical Report, entitled “NI 43-101 Technical Report: Nevada Copper Corp. Pumpkin Hollow Project, Open Pit and Underground Mine Prefeasibility Study”, with an effective date of January 21st, 2019.
Cautionary Language on Forward Looking Statements This news release contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts, are forward-looking statements. Such forward-looking information and forward-looking statements specifically include, but are not limited to, statements that relate to Underground Mine development, production and ramp-up expectations and objectives, future hoisting and production rates, equipment installation, expectations regarding the prefeasibility study update and the expected completion thereof and the other plans of the Company with respect to exploration, development, construction and commercial production.
Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of COVID-19 on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labour disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; dependence on management information systems and cyber security risks; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022. The forward-looking statements and information contained in this press release are based upon assumptions management believes to be reasonable, including, without limitation: no adverse developments in respect of the property or operations at the project; no material changes to applicable laws; the ramp-up of operations at the underground mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of COVID-19 going forward; the Company will be able to obtain sufficient additional funding to complete the ramp-up, no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended.
The forward-looking information and statements are stated as of the date hereof. The Company disclaims any intent or obligation to update forward-looking statements or information except as required by law. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking information and statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. Specific reference is made to “Risk Factors” in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and the quarter ended March 31, 2022 and “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022, for a discussion of factors that may affect forward-looking statements and information. Should one or more of these risks or uncertainties materialize, should other risks or uncertainties materialize or should underlying assumptions prove incorrect, actual results and events may vary materially from those described in forward-looking statements and information. For more information on the Company and the risks and challenges of its business, investors should review the Company’s filings that are available at www.sedar.com.
The Company provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.
YERINGTON, Nev., April 04, 2022 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF)(FSE: ZYTA) (“Nevada Copper” or the “Company”) today announced positive operations advances at its Pumpkin Hollow Project (“the Project”), including record monthly production and continued expectation of up to 5kptd achieved in Q3 as planned, and previously guided.
“We are pleased with the progress continuing to show at Pumpkin Hollow at the underground mine, open pit project, and exploration initiatives”, stated Randy Buffington, CEO and President of Nevada Copper. “The team has done a remarkable job of continuing to safely advance the ramp-up in the key areas of development, stoping, and processing. We look forward to continuing this progress towards steady state production on schedule for later this year.”
March Operations Highlights
Underground Mine
Record Copper Production. In March, as the company continues to improve stoping rates, record copper production was achieved. 1,300dmt of copper concentrates were produced during the last 30 days from multiple stopes, including the high-grade Sugar Cube zone. The commissioning of the paste plant line, planned to be completed in April 2022, along with other operational improvements, is projected to facilitate quicker stope turnover leading to further increases in hoisting and production rates.
3ktpd Hoisting Achieved in March. Peak 7-day continuous hoisting rates reached 2,600 tpd in March, including achieving hoisting of 3ktpd earlier than anticipated which represents a significant production ramp-up progress milestone. Operational focus is on sustaining and increasing the 3ktpd rate in Q2, and the plan remains to reach a capacity of 4.5k to 5ktpd during Q3 2022 as previously announced.
Ramp-up Continues Positive Momentum. Q1 2022 development rates are a 32% quarter-on-quarter increase over Q4 2021. Q1 2022 hoisted ore tons are a 73% quarter-on quarter increase over Q4 2021. Stope ore tons hoisted are a 17% quarter-on-quarter increase over Q4 2021, continuing the trajectory of month-on-month increases over the past 6 months. Enhanced contractor management procedures and key performance indicators are in place to further increase productivity going forward and allow greater access to additional stopes.
Ventilation Infrastructure on site. All surface ventilation infrastructure arrived as planned in Q1 2022. The commissioning of the surface ventilation fans has been optimized to allow for the prioritization of ore development and is planned to be completed in Q2 in line with increased production.
Q2 Milestones to increase ore hoisting rates.
Completion of paste plant commissioning, enabling significantly faster stope cycles
Mining of additional high-grade ore zones
Construction of a third ore pass advanced, which when completed, enables a further increase in ore handling rates towards nameplate capacity
Sequentially higher month-on-month hoisted volumes and concentrate production
Completion of current dike heading to access further higher grade stopes
Previous Constraints Addressed. Most constraints encountered in Q4 2021 and early Q1 2022 have been resolved during Q1. The bolting fleet was refurbished, resulting in demonstrated increases in equipment availability; a damaged remote loader has been scheduled to be replaced shortly; lower contractor delivery was resolved and new KPIs agreed. While these items, plus higher property taxes, increased the cost of ramp-up execution beyond plan, the Company expects to obtain sufficient funds to address these additional costs, including the $15m accordion to its existing Credit Facility.
Open Pit Project
Drill Program has commenced. Drill rigs are scheduled to arrive to site in the coming weeks and drilling to commence this month. The initial focus of the program will be in-fill and extension drilling of the open pit, to follow up on the last drilling program which identified significant additional mineralization and indicated the orebody which remains open in multiple directions, extends beyond the original pit boundary. The drilling program will also provide updated geological information for advancing the fully permitted Open Pit Project into feasibility evaluation reflecting opportunities for increased scale, larger resource and other optimization workstreams. An updated prefeasibility study is expected in Q3 2022 to incorporate the higher copper price environment.
Solar Project Progress. The Company has continued to progress the planned feasibility studies for a potential solar project, with renewables consulting group Warm Springs Consulting.
Exploration
The Company continues to review and evaluate its extensive mineral landholdings at and around Pumpkin Hollow. This ongoing review of the detailed aeromagnetic surveys and continued surface reconnaissance will provide a broader understanding of the geologic model and targeting across Nevada Copper’s land package.
The review will help direct exploration activities in 2022 on newly acquired lands and targets around the existing deposits. The work on the new ground will include surface mapping, sampling, trenching and follow up drilling. The areas of work include the Porphyry, Tedeboy, Mountain View and Black Mountain targets. Geophysical and structural targets around the existing deposits are expected to be followed up with drilling projected to begin in Q3 2022.
Corporate
On March 31, 2022 the Company filed its audited consolidated annual financial statements, the related management’s discussion and analysis and Annual Information Form for the year ended December 31, 2021 on SEDAR.
Qualified Persons The technical information and data in this news release was reviewed by Greg French, C.P.G., VP Exploration of Nevada Copper, Steven Newman, VP Technical Services of Nevada Copper, and Neil Schunke, P.Eng., a consultant to Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.
About Nevada Copper Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
NEVADA COPPER CORP. www.nevadacopper.com
Randy Buffington, President and CEO
For further information contact: Rich Matthews, Investor Relations Integrous Communications rmatthews@integcom.us +1 604 757 7179
Cautionary Language
This news release includes certain statements and information that constitute “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to underground mine development, production and ramp-up expectations and objectives, future hoisting and production rates, equipment installation, expectations regarding obtaining additional funding and the other plans of the Company with respect to exploration and development of the Pumpkin Hollow project.
Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the underground mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the underground mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; dependence on management information systems and cyber security risks; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2021 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 31, 2022. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. The forward-looking statements and information contained in this press release are based upon assumptions management believes to be reasonable, including, without limitation: no adverse development in respect of the property or operations at the Project; no material changes to applicable laws; the ramp-up of operations at the underground mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of COVID-19 going forward; the Company will be able to obtain sufficient additional funding to complete the ramp-up, no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended.
The forward-looking information or statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.
Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.
YERINGTON, Nev., Jan. 25, 2022 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF) (FSE: ZYTA) (“Nevada Copper” or “Company”) is pleased to announce the results from its Special Meeting of shareholders (the “Meeting”) that was held today. The Warrant Exercise Resolution (as defined below), the only item of business at the Meeting, was overwhelmingly approved by disinterested shareholders of the Company. Strong shareholder support for the Warrant Exercise Resolution was evidenced by approximately 99% of the disinterested shareholders who voted at the Meeting voting in favour of the Warrant Exercise Resolution.
Voting Details
At the Meeting, the disinterested shareholders of the Company, being all shareholders of the Company excluding Pala Investments Limited (“Pala”), the Company’s largest shareholder, and Pala’s associates and affiliates, approved an ordinary resolution authorizing (i) the exercise of 15,000,000 common share purchase warrants (the “Credit Facility Warrants”) that were issued to Pala on November 30, 2021 in connection with the amendment and restatement of the credit facility provided by Pala to the Company; and (ii) if some or all of the Credit Facility Warrants are exercised, the resulting issuance by the Company of common shares to Pala pursuant to the terms of the Credit Facility Warrants (the “Warrant Exercise Resolution”). The results of voting on the Warrant Exercise Resolution are provided below:
Votes For
% Votes For
Votes Against
% Votes Against
117,875,484
98.93%
1,275,978
1.07%
About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
Higher highs are on the horizon in 2022 for three critical reasons
A favorable jurisdiction in Nevada- Momentum build and the value proposition is improving
Two groups in the know have made significant investments
The shares continue to offer value, risk-reward favors the upside for Nevada Copper
The leading stock market indices have been bumpy over the past weeks. The prospects for higher interest rates and taxes in 2022, new COVID-19 variants, inflation at the highest level in decades, and other factors have created uncertainty, which tends to cause indigestion in the stock market. However, many leading stocks remain near or at record highs.
Copper is a bellwether commodity that many market participants look to for clues about the health and wellbeing of the global economy. Copper’s nickname is Dr. Copper because it tends to move higher during economic expansion and lower when the global economy contracts. In May 2021, copper rose to its highest price in history when nearby COMEX futures rose to just shy of $4.90 per pound, and LME forwards moved to over $10,700 per ton for the first time. Over the past year, copper has taken on a new role, increasing the demand side of its fundamental equation. The red nonferrous metal is a critical requirement for decarbonization, leading Goldman Sachs to call copper “the new oil.”
In the world of commodities, higher prices and growing demand lead to more production. However, the global copper market faces a challenge as it will take years for new supplies to come to market, creating deficits that push the price higher. While copper corrected since the May high, the price remained around $4.40 per pound level as of December 24.
Locating value in the US stock market is not easy these days. Nevada Copper Corp. (NEVDF) is a promising emerging US producer. Two seasoned commodity groups recently invested in NEVDF, seeing tremendous value in the burgeoning producer.
Copper reached a new high in 2021 Copper closed 2020 at the $3.52 per pound level on the nearby COMEX futures contract and $7,757 per ton on the three-month LME forwards.
Source: CQG
The chart highlights COMEX copper futures move to a high of $4.8985 in May. With the active month March contract at the $4.40 level on December 24, the price moved 25% higher in 2021 with only one week until 2022.
Source: LME
Three-month copper forwards rose to a high of $10,724.50 in 2021 and was at the $9,568 level on December 24, 23.35% higher than at the end of 2020.
While copper is closing 2021 below the year’s high, the trend remains bullish with impressive gains since the end of last year.
Higher highs are on the horizon in 2022 for three critical reasons
Three reasons support higher highs and new all-time peaks in the copper market in 2022 and beyond:
Copper is critical for electric vehicles (EVs), wind turbines, and other clean energy initiatives. The red metal is a crucial ingredient for decarbonization, making the fundamental equation’s demand-side grow.
It takes eight to ten years to bring new copper production online from exploration to output. Copper is still in the early phases of expanding global production, with the leading mining companies scrambling to find new ore deposits. As demand increases, supplies will struggle to keep pace over the coming years.
Inflationary pressures will continue to rise, putting upward pressure on all commodities, and copper is no exception. At the latest December FOMC meeting, the US central bank forecast a 0.90% Fed funds rate for 2022 and a 1.60% rate for 2023. Even if inflationary pressures recede, real interest rates are likely to remain negative, which is bullish for raw material prices in the coming years.
Copper faces an almost perfect bullish storm for the coming years. Goldman Sachs’s forecast of $15,000 per ton by 2025 would put nearly COMEX futures over the $6.80 per pound level. While higher prices will encourage more production, existing mines cannot keep pace with the rising demand.
Chile is the world’s leading copper producer. The recent election of Gabriel Boric, a 35-year-old former student activist who carries a new generation’s socialist dreams to the presidential palace, threatens Chile’s capitalist economy fueled by copper output. Taxes are likely to rise along with wages and addressing climate change could cause a new wave of regulations that weigh on copper output over the coming years. Moreover, the new Chilean government could move to nationalize copper mines, which would impact output and efficiency. The bottom line is that a supply-demand deficit in the global copper market is likely to widen over the coming years, putting upward pressure on the red nonferrous metal’s price.
A favorable jurisdiction in Nevada- Momentum build and the value proposition is improving
The world’s leading copper producers are searching the globe for new reserves and output. Australian mining giant BHP recently said it is considering a challenging Democratic Republic of Congo copper project. The DRC is notorious for political and regulatory issues.
Meanwhile, the US remains a friendly mining environment, and Nevada is a state that supports the industry and is mineral-rich.
Nevada Copper (NEVDF) is an emerging producer with a lot going for it these days. The company mines copper in Nevada in the USA, and the Canadian Fraser Institute ranks the state as the world’s #1 mining jurisdiction. In 2021, momentum has been building for NEVDF:
Underground mine operation improvements have resulted in 100% growth in development rates.
New equipment in the second half of 2021 has accelerated development.
An operational efficiency plan took effect in the second half of 2021 and is forecasted to increase output in H1, 2022.
To put more meat on the bone, in a December 21 press release, the company provided updates on its Pumpkin Hollow underground mine project:
Nevada Copper is on track to advance over 1,100 lateral equivalent feet of development in December 2021.
Development is running at the highest rate for 2021, with December nearly 50% higher than November and almost 100% above the level in August 2021.
New equipment should enhance further development and growth in January 2022.
Ventilation fan infrastructure should be completed in Q1 2022.
Mining of the Sugar Cube, the first high-grade area in the East North Zone of the underground mine, is on schedule for Q1 2022.
In December, CEO Randy Buffington said, “We are on track to complete 1,100 feet of lateral development this month, which puts the Company in a position to mine the first stope of high-grade Sugar Cube as planned next month.”
Accelerated development increases NEVDF’s value proposition:
The current enterprise value is less than the value of the company’s machinery and equipment.
NPV at current prices is close to the US $3 billion level.
The company will be cash-flow positive in 2022.
Open-pit mining development will accelerate in 2022.
The company’s prospects are compelling, leading two influential groups to invest in NEVDF.
Two groups in the know have made significant investments
Solway Investment Group is a private international mining and metals group with headquarters in Switzerland. Solway specializes in nickel production with mines and smelting plants in Guatemala, Ukraine, Russia, Indonesia, and Macedonia. The group has over 5,000 employees, is expanding its focus in battery metals, and recently invested US$30 million for a 10% stake in Nevada Copper.
Mercuria Energy Group Ltd. is a multinational commodity trading company active in global energy, metals, and agricultural markets. The company dates back to 2004 when two ex-Phibro executives, Marco Dunard and Daniel Jaeggi departed after Citigroup sold Phibro to Occidental Petroleum. The company recently closed an oversubscribed $2.2 billion multi-year secured borrowing base credit facility with a collection of international financial institutions. Mercuria is one of the world’s leading and growing commodities trading companies, with core exposure in energy. Mercuria’s goal is a 50% portfolio in renewable energy over the coming five years and invested US$30 million for a 10% stake in Nevada Copper.
Solway and Mercuria are top organizations in the international commodities business, with tentacles reaching across the globe. Both companies put their capital up as they see the compelling potential for Nevada Copper’s properties and business plan.
The shares continue to offer value, risk-reward favors the upside for Nevada Copper
Nevada Copper shares remain inexpensive at the end of December 2021. Aside from the Solway and Mercuria investments, insider buying is another bullish sign for the company. After a recent blackout period, CEO Randy Buffington purchased 200,000 shares, and the company’s directors have been buyers of the shares. Nevada Copper shares (NEVDF) peaked at $2.40 value in May when copper prices reached the high at nearly $4.90 per pound. Copper closed around the $4.40 level on December 23, and NEVDF shares having fallen dramatically in early December hitting yearly lows, could be a golden opportunity for investors that see the same potential as Solway and Mercuria.
Source: Barchart
The chart shows that NEVDF shares corrected to a low of 38.78 cents on October 1 as nearby copper futures moved to test the $4 per pound level. At 53.0 cents per share on December 23, Nevada Copper had a $236.328 million market cap.
Development companies are risky businesses as their future depends on delivering from their mines. The backing of two well-established commodities trading and investment companies, insider buying, and accelerated progress are positive signs for the company as we head into 2022.
New copper production is scarce, and mining companies are scouring the globe for new reserves. Nevada copper’s location, proven and probable reserves, management, progress, and investors bode well for the company’s future. Further progress could transform NEVDF from an emerging producer to a takeover candidate or established producer as the world’s leading miners are hungry for output. Risk is always a function of reward with any investment. At 53.0 cents per share, NEVDF’s potential compensates for the risk.
Any investment involves substantial risks, including, but not limited to, pricing volatility, inadequate liquidity, and the potential complete loss of principal. This document does not in any way constitute an offer or solicitation of an offer to buy or sell any investment, security, or commodity discussed herein, or any security in any jurisdiction in which such an offer would be unlawful under the securities laws of such jurisdiction.
YERINGTON, Nev., Dec. 21, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF)(FSE: ZYTA) (“Nevada Copper” or the “Company”) today provided a further positive operations update at its underground mine at the Company’s Pumpkin Hollow Project (the “Underground Mine”).
December Underground Operations Highlights:
Development Achieves Record Rates
In line with the continued ramp-up, the Company is on track to advance over 1,100 lateral equivalent feet of development in December.
Development is running at the highest rate for 2021, and rates achieved month-to-date in December are almost 50% higher than November (representing almost a 100% increase since August 2021).
Additional Mobile Equipment Delivered and Commissioned
The first planned bolter has been delivered and is now operating underground, resulting in increased development rates and supporting further increases continuing into Q1 2022.
Two additional bolters are on track to be delivered to the underground mine in January enhancing further development rates.
First Delivery of Surface Ventilation Fans Arrived on Site
The first of three deliveries of the ventilation fan infrastructure has arrived on site, with full installation and commissioning continuing to be planned to be completed in Q1 2022.
The final package delivery is expected for the first week of January 2022.
Preparing to Mine Sugar Cube
Mining of the Sugar Cube, the first high-grade area in the East North Zone of the underground mine, continues to be planned for Q1 2022 (News Release, November 30, 2021).
“The Company continues to build on the operational improvements achieved over the past two quarters, providing further acceleration to the development and production ramp-up,” stated Randy Buffington, President and Chief Executive Officer. “The implementation of additional equipment, manpower and operational efficiencies led to the highest development rates attained this year. We are on track to complete 1,100 feet of lateral development this month, which puts the Company in a position to mine the first stope of the high-grade Sugar Cube as planned next month.”
Qualified Persons The technical information and data in this news release was reviewed by Greg French, C.P.G., VP Head of Exploration of Nevada Copper, and Neil Schunke, P.Eng., a consultant to Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.
About Nevada Copper Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.
NEVADA COPPER CORP. www.nevadacopper.com
Randy Buffington, President and CEO
For further information contact: Rich Matthews, Investor Relations Integrous Communications rmatthews@integcom.us +1 604 757 7179
Cautionary Language
This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to mine development, production and ramp-up objectives and equipment installation.
Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. The forward-looking information or statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.
Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.