Categories
Breaking Energy Granite Creek Copper Junior Mining Metallic Group

Granite Creek Copper Announces Positive PEA with Net Present Value of $324M on Carmacks Copper-Gold Project in Yukon, Canada

Granite Creek Copper, Proven and Probable

VANCOUVER, BC / ACCESSWIRE / January 19, 2023 / Granite Creek Copper Ltd. (TSXV:GCX)(OTCQB:GCXXF) ( “Granite Creek” or the “Company” ) is pleased to report positive results from its Preliminary Economic Assessment (“PEA”) for the Carmacks Copper-Gold-Silver project (the “Project” or “Carmacks Project”), located in the Yukon, Canada’s Minto Copper District within the traditional territories of Little Salmon/Carmacks First Nation and Selkirk First Nation.

The PEA demonstrates attractive project economics with significant opportunities for additional mine life expansion, reinforcing the potential of the Minto Copper District to become a top-tier global copper district.

Granite Creek Copper will be hosting a live webinar to review the PEA results on January 24th , 2023, at 9:00am PT | 12:00PM ET. To register, click here .

PEA Highlights

  • Attractive project economics:
    • Base case metal prices of US$3.75/lb Cu, US$1,800/oz Au and US$22/oz Ag:
      Pre-tax NPV 5% of C$324 million and 36% IRR
      After-tax NPV 5% of C$230 million and 29% IRR
    • Case 1 metal prices of US$4.25/lb Cu, US$2,000/oz Au and US$25/oz Ag:
      Pre-tax NPV 5% of C$475 million and 48% IRR
      After-tax NPV 5% of C$330 million and 38% IRR
  • Mine life of nine years at 7,000 tonnes per day with clear exploration potential to extend mine life with four target areas within 1km of the current resource.
  • Capital cost of C$220m with payback of 2 years from commencement of production.
  • Head grade of 1.10% copper equivalent (“CuEq”) consisting of 0.90% Cu, 0.30 g/t Au and 3.5 g/t Ag.
  • Average cash operating costs of US$1.76/lb CuEq and all-in sustaining costs of US$2.57/lb CuEq.
  • Option for tailings treatment: PEA study identifies additional potential cash flow through processing of oxide tailings to increase total copper recovery. Recovery sensitivity shows an additional $180M pre-tax NPV based of a 20% increase in recovery rates.

The Company envisions developing the Carmacks Project into a low-carbon source of copper. A critical mineral, as defined by the Canadian government, copper is key to the transition to a zero-carbon economy through the electrification of transportation and other industries, and the development of renewable energy production. The 2023 PEA clearly demonstrates the viability of the Carmacks Deposit as a robust open pit sulphide and oxide copper-gold-silver project with significant potential upside from both resource expansion and secondary processing of oxide material to further improve oxide recoveries. The Project is to be powered by the Yukon’s electrical grid which uses primarily renewable electricity.

“The completion of the PEA is a major accomplishment that doesn’t just advance the Project beyond previous studies but completely re-envisions Carmacks as a high-grade, open pit copper, gold and silver producer with excellent expansion potential in a tier one jurisdiction”, commented Timothy Johnson, President and CEO. “The inclusion of sulphide alongside oxide ore, either as a blend or a straight sulphide feed, has resulted in significant upside on the Project, with further opportunities recognized in both processing and exploration.”

“Potential for near mine resource expansion is demonstrated in new volumetrically significant targets identified by comparison of the geophysical signatures of known mineralization with similar signatures of untested targets near the proposed pits “, continued Mr. Johnson. “These strong geophysical responses have a high correlation with copper sulphide minerals on the Project, giving us high confidence in these new targets, which are a priority for testing in upcoming drill campaigns.”

PEA Study Approach

The PEA contemplates open pit mining using a conventional truck and shovel operation in two separate pits. Mining targets the high-grade, near surface oxide material in the 147 pit, then transitions to target sulphide material in the 1213 pit followed by final mining of the deeper oxide and sulphide material in 147. Mined material would be delivered to a crushing and grinding circuit consisting of a primary crusher, SAG mill and ball mill. Both oxide copper ore and sulphide copper ore would be processed via a simplified flow sheet consisting of well-established flotation technology producing a high-quality copper-gold-silver concentrate. Oxide and sulphide ore would be blended and sequenced to provide optimal cash flow and to minimise the environmental footprint with mined-out pits or portions of pits being reclaimed as mining commences in the next area. Both conceptual pits lie within 2km of the proposed mill site.

Tailings from the flotation circuit would be filtered and water recirculated into the flotation circuit. This would improve water management and limit environmental impact, with final tailings placement on a lined dry stack tailings facility at site.

A high-grade, premium copper, gold and silver concentrate would be shipped via deep seaports in Skagway, Alaska or other nearby facilities. Treatment and refining charges terms are within standard market rates.

Average copper recovery during life of mine (“LOM’) is calculated to be 64% with approximately 2/3 of material processed being oxide ore and 1/3 being sulphide ore. Metallurgical studies returned 93% copper recovery when processing sulphide ore, 40% copper recovery while processing oxide ore and 82% when processing a 50:50 blend. Metallurgical work highlights the opportunity for further optimization of the Project through more detailed mine sequencing or discovery of near mine sulphide or that could be blended with ore from the 147 pit.

Table 1: PEA Key Parameters

ParameterUnitBase Case 1Case 1
Metal Prices
Copper PriceUS$/pound$3.75$4.25
Gold PriceUS$/troy ounce$1,800.00$2,000
Silver PriceUS/troy ounce$22.00$25
Average Recovery to Cu Concentrate 2
Copper Recovery%64%
Gold Recovery%58%
Silver Recovery%60%
Concentrate Grade
Copper%40%
Goldg/t11.0 g/t
Silverg/t134.4 g/t
Production Data
Resource Tonnes21,270,518
Copper Equiv. Grade1.10%
Daily Mill ThroughputTonnes / day7,000 t7,000 t
Annual Processing RateKilo tonnes/ year2,495 kt2,495 kt
LOM Strip ratioWaste: Ore4.6:14.6:1
Mine LifeYears9 years9 years
Average annual production
Copper EQ production 6Million Pounds / year33.9 M
Copper in concentrateMillion Pounds / year27 M
Gold in copper concentrateTroy ounces / year12 385
Silver in copper concentrateTroy ounces / year151 584
Operating Costs (LOM avg) 2
MiningC$/t mined$3.16
MillingC$/t processed$18.30
G&AC$/t processed$4.93
All in Sustaining Costs 4,5US$/lb CuEq$2.57
Capital Costs
Initial Capital CostC$C$220M
LOM Sustaining Capital CostC$C$130M
Financial Analysis
Pre-Tax NPV 5%C$C$324MC$475M
Pre-Tax IRR%36%48%
After Tax NPV 5%C$C$228MC$330M
After Tax IRR%29%38%
Payback period 7Years2.01.5
  1. Base case metal prices based on 36-month trailing average from January 15, 2022.
  2. Recovery includes both oxide and sulphide ore and is based on mining 2/3 oxide and 1/3 sulphide LOM.
  3. Total operating costs include mining, processing, tailings, surface infrastructures, transport, and G&A costs.
  4. AISC includes cash operating costs, sustaining capital expenses to support the on-going operations, concentrate transport and treatment charges, royalties and closure and rehabilitation costs divided by copper equivalent pounds produced.
  5. AISC is a non-IFRS financial performance measures with no standardized definition under IFRS. Refer to note at end of this news release.
  6. The copper equivalent grade (CuEq) is determined by (total copper x US$3.75) + (total gold x US$1800) + (total silver x $22)/$3.75)/total resource tonnes.
  7. Payback period is from commencement of mining.

Capital Cost

The PEA for the Project outlines an initial (pre-production) capital cost estimate of C$220 million and LOM sustaining capital costs of C$130 million, including overall closure costs of C$5 million. Initial capital costs include the construction of milling and processing facilities, lined dry stack tailings and lined waste rock facilities, on-site infrastructure of 15km of access road and facilities for water capture and treatment. Construction of a powerline (12.8 km, 138 kV) from an existing substation is placed under sustaining capital to allow for construction time of the power grid.

Table 2: Capex Estimates 1

Cost ElementBase Case
Mine CostsC$25M
ProcessingC$84M
InfrastructureC$27.7M
TailingsC$14.7M
EPCM and Indirect CostsC$34.1M
Sub total CapexC$185 M
Sustaining CapitalC$130.M
ContingencyC$35.0M
Reclamation and ClosureC$5.0M

1 All values stated are undiscounted.

Operating Costs

Operating costs estimates were developed using first principles methodology, vendor quotes received in Q3 2022, and productivities being derived from benchmarking and industry best practices. Over the LOM, the average operating cost for the Project is estimated at C$3.16/t mined and C$18.30/t processed. Tailings costs are included in processing costs.

The average cash operating costs over the LOM is US$1.76/lb CuEq and the average AISC is US$2.57 /lb CuEq.

Economic Analysis and Sensitivities

The PEA indicates that the potential economic returns from the Project justify advancing to a feasibility study.

The Project generates cumulative cash flow of C$371.2 million on an after-tax basis and C$505.8 million pre-tax at a base case of $3.75/lb Cu based on an average mill throughput of 7,000 t/day over the 9-year life of mine.

Table 3: Summary of Economic Analysis 1,2

ElementBase CaseCase 1
Metal Price Assumptions (US$) Copper, Gold Silver$3.75, $1800, $22$4.25, $2000, $25
Exchange Rate0.750.75
Average annual cash flowC$61.8MC$76.9M
Payback Period2.5 years1.5 years
EBITDAC$505.8MC$710M
LOM Undiscounted Net Cash Flow After TaxC$371.2MC$505M
NPV (5% discount) After TaxC$230.5MC$328M
IRR After Tax29%38%

1 The analysis assumes that the Project is 100% equity financed (unlevered).
2 Appropriate deductions are applied to the concentrate produced, including treatment, refining, transport and insurance costs.

The PEA is significantly influenced by copper price assumptions. Using the Case 1 metal price scenario consists of near current prices of US$4.25/lb Cu, US$2000/oz Au and US$25/oz silver, the Project generates an after-tax Net Present Value (“NPV”) using an 5% discount rate of $328 million and an after-tax IRR of 38% with a payback period of 1.5 years from the commencement of production. (Table 3), Outlined below in Table 4 is a detailed sensitivity analysis across gold and copper prices with silver kept at $22/ounce. Table 5 below highlights additional sensitivities to foreign exchange, recovery, CAPEX and OPEX.

Table 4: Copper and Gold Metal Price Sensitivity Analysis NPV- Pre-Tax values in Million CDN$

Copper Price per pound US$
Gold price per ounce
US$ 1
3.253.503.75
Base Case
4.004.25
Case 1
4.50$4.75$5.00$5.25
1500$165.7$227.6$289.4$351.3$413.1$474.9$536.8$598.6$660.5
1600$177.3$239.1$301.0$362.8$424.7$486.5$548.3$610.2$672.0
1700$188.9$250.7$312.5$374.4$436.2$498.0$559.9$621.7$683.6
1800 Base$200.4$262.2$324.1$385.9$447.8$509.6$571.4$633.3$695.1
1900$212.0$273.8$335.6$397.5$459.3$521.1$583.0$644.8$706.7
2000 Case 1$223.5$285.3$347.2$409.0$470.9$532.7$594.5$656.4$718.2
2100$235.1$296.9$358.7$420.6$482.4$544.3$606.1$667.9$729.8
2200$246.6$308.4$370.3$432.1$494.0$555.8$617.6$679.5$741.3

Table 5: Multiple variable sensitivity analysis (all values $CDN)

VariablePre-Tax NPV 5%After – Tax NPV 5%
-20 %Base+20%-20 %Base+20%
Copper Price$138.6M$324.1M$509.6M$88.3M$230.5M$361.0M
FX Rate$129.7M$324.1M$615.6M$118.6M$230.5M$381.8M
Recovery$138.6M$324.1M$509.6M$88.3M$230.5M$361.0M
CAPEX$381.9M$324.1M$266.2M$243.5M$230.5M$215.6M
OPEX$452.2M$324.1M$196.0M$318.9M$230.5M$131.2M

Opportunities

  • The third conceptual pit, 2000S as identified in the Mineral Resource Estimate (“MRE), could be brought into the mine plan if sufficient additional resources were defined by drilling to offset pre-stripping costs.
  • Electrification of the mining fleet. Significant cost saving and reduction in greenhouse gas production may be possible through the sourcing of electric vs. diesel haul trucks for the Project. The PEA envisions using a contract mining fleet for the Project and preference will be given to suppliers that can provide either fully electric or hybrid equipment.
  • Further discovery. Exploration conducted in 2022 consisting of geophysics, trenching and soil sampling identified four areas proximal to the proposed mine plan that if successfully drilled could enable longer mine life beyond nine years or provide additional sulphide mill feed earlier in the mine’s life. Four targets on the Property require evaluation, all located within 1km of the current deposits. Two of the targets are located beneath the current resource and there is higher geological certainty that these may contain appreciable copper mineralization.
    • Zone 1213 shallow:
      Downward continuation of Zone 12 and 13. Estimated dimensions are 360m long, 15 – 40m wide, starting at approximately 65m below the current drilling.
    • Zone 12 deep:
      Downward continuation of Zone 12. Estimated from geophysics to be continuing for an additional 170m below current resource modelling. Approximated to be 580m long and 15-40m wide.
    • Gap Zone target:
      Geophysical anomaly that fits with current geological understanding of the fault offset between 147 and 2000S Zone. Estimated to be 500m long, up to 400m deep, and 30-50m wide.
    • Sourtoe target:
      Estimated from geophysics to be a lensoidal body of similar size to known deposits at 370m long x 370m deep with an estimated width of 15-50m. It has been lightly tested at surface by trenching and is weakly mineralized.
  • In addition, the Carmacks North target area is host to several mineralized zones that have the potential to add resources to the mine plan, all within 15 km of the proposed mill site.
  • Additional recovery through metallurgical improvements. The Company has retained Kemetco Laboratories to complete additional leaching and copper precipitating testing to evaluate the processing of tailings. The calculated grade of copper in tailings averages 0.32% with over 140 Mlbs of copper not recovered LOM. Recovery sensitivity show an additional $180M pretax NPV based of a 20% increase in recovery rates. Review of historical metallurgical testing has indicated that copper minerals present in oxidized material respond well to leaching. Once the copper is in solution the copper would be chemically precipitated to produce sulphide minerals that can be added back into the flotation cells.

Mineral Resources

The basis for the PEA uses an updated mineral resource estimate (“MRE”) for the Carmacks deposit (effective date March 30, 2022). The mine plan contemplates processing 62% of resources outlined in the MRE. The MRE includes inferred resources that are too speculative to have economic parameters applied to them. Resources are not reserves and there is no certainty that the resources outlined on the Project can be converted to reserves.

Table 6: Mineral Resource Estimates

CATEGORYCut -Off
Cu (%)
Quantity (Mt)Grade
Cu†AuAgMoCuEq
Total (%)(g/t)(g/t)(%)Total (%)
In Pit Oxide
Measured0.3011.3610.960.404.110.0061.30
Indicated0.304.3300.910.283.370.0071.16
Measured &Indicated0.3015.6910.940.363.910.0061.26
Inferred0.300.2160.520.092.440.0060.63
In Pit Sulphide
Measured0.305.7050.680.162.540.0160.88
Indicated0.3013.4860.720.192.830.0130.93
Measured &Indicated0.3019.1910.710.182.740.0140.92
Inferred0.301.6750.510.132.240.0200.70
Below Pit Sulphide
Measured0.600.0260.710.162.540.0100.88
Indicated0.601.3410.820.192.880.0121.03
Measured &Indicated0.601.3670.820.192.880.0121.03
Inferred0.600.9670.770.172.480.0120.96

Notes:

  1. CIM (2014) definitions were followed for Mineral Resources.
  2. The effective date of the Mineral Resources is March 30, 2022.
  3. Mineral Resources are estimated using an exchange rate of US$0.75/C$1.00.
  4. Mineral Resources are estimated using a long-term gold price of US$1,800/oz Au with a metallurgical gold recovery of 60%, and a long-term copper price of US$3.75/lb with a metallurgical copper recovery of 95% for sulphide material and 60% for oxide material.
  5. Mineral Resources are estimated at a cut-off grade of 0.30 copper equivalent.
  6. Bulk density of 2.83 t/m 3 was used for tonnage calculations.
  7. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
  8. Numbers may not add up due to rounding.

Mining

The overall mining operation is expected to consist of two open pits completed over three phases. Phase I contemplates development of the 147 zone with low strip ratio. Phase 2 contemplates the mining of 1213 zone with a slightly higher strip ratio. Phase 3 contemplates pushback on the 147 pit to a final LOM strip ratio of 4.6:1, resulting in a total of 9 years of operation, plus one year of pre-stripping. Following this mining period, a low-grade stockpile of 2Mt grading 0.18% Cu, 0.06 g/t Au and 0.8 g/t Ag may be reprocessed once mining operations cease. All waste and tailings will be disposed near the mining infrastructure.

The contract mining operation is planned to be a conventional truck and shovel open pit operation, moving approximately 118Mt of material over the 9-year life of mine. This would provide the floatation processing plant with 21.3Mt of ore at a rate of 7 000 tonnes per day.

Metallurgy and Processing

The processing facilities and saleable mineral products are fundamentally different from the beneficiation procedures that were contemplated in the 2006 Feasibility Study and updated in the 2017 PEA. The processing facilities currently being recommended for the Project would include a simplified flotation circuit, capable of processing three individual types of feed materials, oxide, sulphide, and blended ores, each of which would produce a high grade, premium concentrate.

Metallurgical testing both by Bureau Veritas in 2021 and by SGS Vancouver in preparation for the PEA study support the simplified flotation circuit. Flotation testing of individual oxide copper ores, sulphide copper ores as well as blended ores has been completed in this initial phase of the process investigation.

A test program including mineralogy and flotation was completed on samples from the Carmacks Project. The flotation test program included test work on sulphide, oxide, and blend ores.

  • The sulphide ore assayed 0.92% Cu, 0.67% S, and 0.24 g/t Au. Gold and copper head grades calculated from the flotation test assays agreed well with the direct head assays.
  • The oxide ore assayed, 0.60% Cu, 0.06% S, and 0.25-0.82 g/t Au, indicating that nugget gold may exist. However, the gold head grade calculated from the flotation tests was consistently between 0.20 g/t to 0.23 g/t with an average of 0.21 g/t.
  • Sulphide flotation recovered 93.7% of copper and 69.0% of gold at 42.7 % Cu and 7.7 g/t Au grade (Sulphide F4) while oxide flotation recovered 39.8% of copper and 57.5% of gold at 26.2% Cu and 13.6 g/t Au grade.
  • A 50/50 oxide/sulphide blend batch flotation program recovered 75.3% of copper and 65.7% of gold at 40.8 % Cu and 12.4 g/t Au grade (Blend F4).
  • Locked cycle flotation on blend sample recovered 82.0% of copper and 70.1% of gold at 40.1% Cu and 10.6 g/t Au grade (Blend LCT1).
  • Flotation optimization and an economical evaluation of the target copper grade versus recovery is recommended in future test work.

As mentioned above, the Company has commissioned additional test work to evaluate the potential for further recovery of copper from tailings when material in the mill contains a significant percentage of oxide material. Review of historical metallurgical testing has indicated that copper minerals present in oxidised material respond well to leaching. Once the copper is in solution the copper will be chemically precipitated to produce sulphide minerals that can be added back into the flotation cells.

Infrastructure

The Project lies along the Freegold Road, a Yukon government-maintained gravel road, currently being upgraded as part of the Yukon Resource Gateway Program. The road would ultimately lead to the near by Casino Project and other significant development projects in the area. A 12.8 km transmission line would be constructed to access the 138 kV Carmacks-Stewart transmission at McGregor Creek. Future studies will look at alternate routes for powerlines that could also benefit projects near the proposed Carmacks Project.

Next Steps

Additional Metallurgical work. In addition to the metallurgical work underway to assess further recovery from tailings work will be completed to optimise recoveries of both copper and precious metal. Additional studies will also be completed to identify any metallurgical variability between the two proposed mining areas to assist in further mine plan optimization through sequencing and blending of ore.

Exploration Drilling. Significant resource expansion potential exists within 1 km of the proposed pits. In addition to the new zones identified by 2022 geophysical and geochemical surveys, and trenching, many areas of both the 2000S and 12-13 zones remain open for expansion.

Geotechnical drilling on 1213 pit. In order to advance the Project towards feasibility geotechnical drilling will need to be completed on the proposed 1213 pit. Significant geotechnical drilling in the 147 area dating back to 2006 when a full feasibility study was completed on that portion of the Project will also be reviewed.

Baseline environmental studies. In preparation for advancing the Project towards feasibility existing environmental studies including ongoing water sampling programs will be reviewed and updated.

Continued community engagement. The Company is dedicated to working with communities effected by the Project including Little Salmon Carmacks First Nation and Selkirk First Nation to ensure that the Project advances in a respectful way with maximum benefit to the effected communities.

Technical Report and Qualified Persons

The PEA was prepared by SGS Geological Services. (“SGS”). with several individuals and departments within SGS contributing to sections of the study. William Van Breugel P.Eng., is the lead consultant for this study. SGS Geological Services is known globally as the expert in ore body modelling and resource/reserve evaluation with over 40 years and 1000 consulting projects of experience providing the mining industry with computer-assisted mineral resource estimation services using cutting edge geostatistical techniques. SGS bring the disciplines of geology, geostatistics, and mining engineering together to provide accurate and timely mineral project evaluation solutions.

As part of the larger SGS Natural Resources group, they draw upon their massive network of laboratories, metallurgists, process engineers and other professionals to help bring mineral projects to the next level.

Table 7: Qualified Person

DepartmentArea of ResponsibilityQualified Person
SGSMine DesignJohnny Canosa, P.Eng and William Van Breugel, P.Eng
Mine InfrastructureJohnny Canosa, P.Eng
SGS TucsonMetallurgy. Processing and process plant operating costsJoseph Keane PE
SGS TucsonProcess plant and infrastructure capital costsJoseph Keane PE
Financial analysisWilliam Van Breugel, P.Eng

Note: The Qualified Persons are independent as defined by Canadian Securities Administrators National Instrument 43-101 (“NI 43-101”) “Standards of Disclosure for Mineral Projects”. The Qualified Persons are not aware of any environmental, permitting, legal, title, taxation, socio-economic, marketing, political, or other relevant factors that could materially affect the PEA.

The Company cautions that the results of the PEA are preliminary in nature and do not include the calculation of mineral reserves as defined by NI 43-101. There is no certainty that the results of the PEA will be realized.

A NI 43-101 technical report supporting the PEA will be filed on SEDAR within 45 days of this news release and will be available at that time on the Company’s website. Readers are encouraged to read the Technical Report in its entirety, including all qualifications, assumptions and exclusions that relate to the details summarized in this news release. The Technical Report is intended to be read as a whole, and sections should not be read or relied upon out of context.

A presentation summarizing the Project’s PEA results is available on the Company’s website.

Qualified Persons

All scientific and technical data contained in this presentation relating to the PEA has been reviewed and approved by William Van Breugel P.Eng., a Qualified Person for the purposes of NI 43-101. All exploration data including exploration upside potential has been reviewed and approved by Debbie James P.Geo., for the purposes of NI 43-101 The Qualified Persons mentioned above have reviewed and approved their respective technical information contained in this news release.

About Granite Creek Copper

Granite Creek, a member of the Metallic Group of Companies, is a Canadian exploration company focused on the 176-square-kilometer Carmacks Project in the Minto Copper District of Canada’s Yukon Territory. The Project is on trend with the high-grade Minto copper-gold mine, operated by Minto Metals Corp., to the north, and features excellent access to infrastructure with the nearby paved Yukon Highway 2, along with grid power within 12 km. More information about Granite Creek Copper can be viewed on the Company’s website at www.gcxcopper.com .

FOR FURTHER INFORMATION PLEASE CONTACT:

Timothy Johnson, President & CEO
Telephone: 1 (604) 235-1982
Toll-Free: 1 (888) 361-3494
E-mail: info@gcxcopper.com
Website: www.gcxcopper.com
Twitter: @yukoncopper

Forward-Looking Statements

This news release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, potential economic estimates, capital costs, operating costs, potential cash flows, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the Company are forward-looking statements that involve various risks and uncertainties. Although Granite Creek Copper believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Granite Creek Copper and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com .

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Granite Creek Copper Ltd.

Categories
Base Metals Energy Exclusive Interviews Junior Mining Metallic Group Precious Metals Stillwater Critical Minerals

Stillwater Critical Minerals – Reports High-Grade Gold, Platinum Group Elements, Battery Metals

Stillwater Critical Minerals (TSX.V: PGE | OTC: PGEZF)
Website | https://criticalminerals.com/
Corporate Presentation | https://criticalminerals.com/investors/presentations/
Stillwater Critical Minerals
Suite 904 – 409 Granville Street
Vancouver, BC V6C 1T2

Tel: +1 (604) 357-4790
Toll Free: +1 (888) 432-0075
Email: “Chris Ackerman (Critical Minerals)” cackerman@criticalminerals.com


The Best Video on Why and When to Buy and Sell Physical Precious Metals:

This image has an empty alt attribute; its file name is image-2-1024x263.png

WEEKLY SPECIAL: JAN 2023

This image has an empty alt attribute; its file name is valcambi_special_mf-1024x576.jpg
This image has an empty alt attribute; its file name is krugerrand_promo_mf-1024x576.jpg
https://www.milesfranklin.com/faq-maurice/
This image has an empty alt attribute; its file name is BitcoinSidebar.png.pagespeed.ce.6z1FEqVkO4.png

I’m a licensed broker for Miles Franklin Precious Metals InvestmentsThe Only Online Dealer that is Licensed and Bonded Period! Where we provide unlimited options to expand your precious metals portfolio, from:

Website| www.provenandprobable.com
Call me directly at 855.505.1900 or email: Maurice@MilesFranklin.com
Precious Metals FAQ – https://www.milesfranklin.com/faq-maurice/

Categories
Base Metals Energy Exclusive Interviews Junior Mining Metallic Group Metallic Minerals Precious Metals

Metallic Minerals – Releases 2022 Drill Results on Keno Silver Project

Metallic Minerals: TSX.V: MMG | OTC: MMNGF)

Website:https://mmgsilver.com/

Corporate Presentation: https://mmgsilver.com/investors/presentations/

Investor Relations: Chris Ackerman Senior Manager – Corporate Communications & IR Email: chris.ackerman@metallic-minerals.com Phone: 604-629-7800 ext. 1 Toll Free: 1-888-570-4420

Press Release: https://mmgsilver.com/news/2023/metallic-minerals-intercepts-144.5-meters-of-41.4-g-t-ag-eq-as-bulk-tonnage-ag-pb-zn-zone-emerges-as-resource-target-at-fox-in/

The Best Video on Why and When to Buy and Sell Physical Precious Metals:

WEEKLY SPECIAL: JAN 2023

https://www.milesfranklin.com/faq-maurice/

I’m a licensed broker for Miles Franklin Precious Metals InvestmentsThe Only Online Dealer that is Licensed and Bonded Period! Where we provide unlimited options to expand your precious metals portfolio, from:

Website| www.provenandprobable.com
Call me directly at 855.505.1900 or email: Maurice@MilesFranklin.com
Precious Metals FAQ – https://www.milesfranklin.com/faq-maurice/

Categories
Base Metals Energy Junior Mining Metallic Group Metallic Minerals Precious Metals

Metallic Minerals Intercepts 144.5 Meters of 41.4 g/t Ag Eq as Bulk-Tonnage Ag-Pb-Zn Zone Emerges as Resource Target at Fox in East Keno, Keno Silver Project, Yukon, Canada

VANCOUVER, BC / ACCESSWIRE / January 12, 2023 / Metallic Minerals Corp. (TSX.V:MMG)(OTCQB:MMNGF) (“Metallic Minerals” or the “Company”) is pleased to announce initial assay results from the 2022 field program at the Keno Silver project located in the historic Keno Silver district of the Yukon; Canada’s most important silver mining district. These results cover the East Keno area and represent the first in a series of results to be released from the Company’s 2022 exploration program, which included 3,265 meters (m) of diamond core drilling in 23 drill holes focused on expansion of advanced stage, “resource-ready” targets in anticipation of an inaugural NI 43-101 mineral resource estimate in 2023.

Exploration in 2022 at East Keno focused on drilling of the Greater Fox area targets (Fox, UKHM and Zone 2) first discovered by the Company in 2020, through systematic exploration efforts including mapping, geochemical soil sampling, geophysics, and drilling (see Figure 1). This work outlined the first known occurrence of Ag-Pb-Zn sheeted veins and includes the widest intervals of continuous mineralization ever reported in the Keno Hill silver district at up to 177 meters thickness. The sheeted vein mineralization (spaced distinct parallel Ag-Pb-Zn veins) at Fox is found in geologic settings that may be repeated as significant additional targets across the property which, as yet remain undrilled. The East Keno target areas of Fox, UKHM and Zone 2 have become substantial advanced-stage targets, poised for further expansion drilling and near-term resource delineation.

2022 East Keno Exploration Highlights

  • Mineralization was intercepted in each of the eight holes (1,386 m) drilled at East Keno in 2022 (see Table 1). Both bulk-tonnage and high-grade Ag-Pb-Zn vein-style mineralization was encountered.
  • Drill intercepts at the Fox target in 2022 averaged 136 m of sheeted vein mineralization (including up to 177 m wide); a significant broadening of the identified mineralized zones encountered in 2020 and 2021 drilling at Fox.
  • At the Fox target, hole FOX22-03, returned sheeted vein zones of 144.5 m @ 41.4 g/t silver equivalent (Ag Eq), including 27.66 m at 105.8 g/t Ag Eq.
  • A total of 107 high-grade samples (over 100 g/t Ag Eq and greater than 0.5 m in width) were intercepted in in the 2022 East Keno drilling, including:
    • Z222-01, 0.5 m @ 222.7 g/t Ag Eq (182 g/t Ag, 1.10% Pb, 0.03% Zn)
    • FOX22-02, 0.5 m @ 806.9 g/t Ag Eq (555.0 g/t Ag, 3.24% Pb, 3.14% Zn)
    • FOX22-03, 0.59 m @764.0 g/t Ag Eq (463.0 g/t Ag, 0.23 g/t Au, 0.79% Pb, 5.41% Zn)
    • UKHM22-01, 0.55 m @1087.0 g/t Ag Eq (953.0 g/t Ag, 3.56% Pb, 0.28% Zn)

Metallic Minerals President, Scott Petsel, stated, “The 2022 drilling at Fox is indicative of the huge potential at East Keno and has significant implications for further exploration success and future resource development. The sheeted Ag-Pb-Zn vein system identified at Fox had not been recognized in the district prior to Metallic’s systematic exploration efforts and our team has since identified additional new areas as potential hosts of similar mineralization. We have now extended mineralization at the Fox deposit over 300 m along strike and 150 m down-dip starting from surface, where it remains open in all directions. A total of 18 drill holes define the Fox zone and show good continuity of the broader mineralized system with a relatively shallow dip. Resource modelling is currently underway focused on the large-scale bulk-tonnage resource potential for the Fox target area.”

“The Company expects to announce additional drill results from both the Keno Silver Project (Primarily at advanced stage targets Formo and Caribou) and the La Plata Cu-Ag Project over the coming weeks and we look forward to discussing these and other developments at events throughout Q1.”

2023 AMEBC Mineral Roundup Core Shack

Metallic is very pleased to announce that we have been invited to participate in this year’s AMEBC Mineral Roundup conference in Vancouver and will be displaying intervals of drill core from the Keno Silver project and our La Plata Project on Wednesday, January 25th and Thursday, the 26th. Key members of our management and technical teams will be on hand to discuss the project and opportunity. Visit us at booth #1016 in the Core Shack. For more information and to register, visit here.

Vancouver Resource Investment Conference – Presentation

Metallic President, Scott Petsel, will be providing a corporate update and participating in a moderated roundtable discussion during the upcoming Vancouver Resource Investment Conference on Sunday, January 29th at 3:30 PM in the Yukon Pavilion. For more information, visit here.

Figure 1. Keno Silver District Geology and Deposits

Metallic Minerals Corp., Thursday, January 12, 2023, Press release picture
Metallic Minerals Corp., Thursday, January 12, 2023, Press release picture

East Keno Target Areas – Fox, Zone2 and UKHM

The East Keno area is represented by 15 multi-kilometer scale soil and geophysical anomalies which indicate additional potential for broad-scale mineralization in the least explored part of the Keno Hill silver district. Five of these anomalies have been drilled with initial positive results and an additional five other targets are drill ready. The Fox target, now with 2,748 meters drilled in 18 holes over three years, will be the focus of continued expansion and resource definition drilling in future programs.

Exploration of the East Keno area by Metallic Minerals began in 2018 with soil geochemical sampling and progressed to initial reverse circulation drilling in 2020 which returned several significant high-grade Ag-Pb-Zn sulfide vein intervals (KE20-01 0.77m @ 1,397 g/t Ag Eq) and numerous broad bulk-tonnage scale intervals (KE20-01, 28.2 @ 64 g/t Ag Eq and KE20-02, 22.1 m @ 48 g/t Ag Eq). The 2021 field program in East Keno combined additional reverse circulation drilling and initial diamond core drilling in warranting additional confidence in the target areas.

Drilling combined with extensive mapping and other geologic data has demonstrated a transition at East Keno from north to south from typical Keno style Ag-Pb-Zn mesothermal mineralization at Fox to mixed mesothermal and epithermal styles of mineralization at Zone 2 and UKHM. Epithermal mineralization is often associated with higher silver grades as demonstrated on the west side of the district at Silver King and Husky SW. The broad zones of mineralization at Fox, are now recognized as shallow dipping high-grade sheeted mesothermal Ag-Pb-Zn veins that appear to be associated with a regional scale thrust fault structures. This is a target concept that is broadly repeated across the district, and more specifically at multiple untested targets in the East Keno area.

Mineralized widths from the 2022 drilling on the Fox target returned the widest zones of continuous mineralization ever reported in the Keno Hill silver district and on a grade thickness basis are comparable in contained metal with some of the richest zones from the western part of district (see detailed 2022 results in Table 1 below). The Fox deposit sits within a multi-kilometer scale silver-in-soil anomaly leaving significant room to grow the footprint of mineralization for the Fox target both laterally and down dip. The westernmost drilling in the Fox target area, FOX22-05 and FOX22-06, demonstrates increasing widths of mineralization that will be tested in future programs along with untested areas of very high-level silver in soil values.

Drilling at the earlier stage Zone 2 and the UKHM targets have returned significant silver values including broad envelopes of mineralization similar to the Fox zone along with narrower high-grade silver intervals typical of the district. All drilling on these early-stage targets has been at shallow depths and these targets remain open for expansion with further drilling (see 2022 results in Table 1 below).

2022 East Keno Drilling

The focus of the 2022 drilling at Fox was extend known outlines of mineralization to enhance potential near-term resource opportunities. Single drill holes at UKHM and Zone 2 further confirmed these areas, both broad-scale mineralization and higher-grade epithermal style Ag-Pb-Zn veins, as priority targets for significant additional drilling and focus (See Figure 2).

Table 1 – Highlights of 2022 Drill Results from the East Keno Target Areas

Bulk Tonnage Intervals
HoleFrom (m)To(m)Length (m)Ag Eq1(g/t)Ag(g/t)Au (g/t)Pb(%)Zn (%)
FOX22-0111.8147.75135.9525.87.90.010.030.33
incl5179.728.747.114.50.020.040.62
FOX22-0215.3191.88176.5816.56.40.000.030.18
incl6978.59.576.531.10.010.190.83
and incl174.81186.811252.215.50.000.040.75
FOX22-0315159.5144.541.414.60.010.040.52
incl29.55101.7572.268.122.60.010.060.89
and incl74.09101.7527.66105.829.50.020.091.54
FOX22-0428.9154.3125.436.210.60.010.030.50
incl28.9114.8585.9549.314.80.010.050.67
and incl67.48114.8547.3773.921.60.010.071.06
FOX22-0511.24117105.7615.74.00.010.010.20
incl27.9682.5554.5921.05.00.010.010.28
FOX22-061013612633.57.60.0080.020.51
incl65117.1552.1563.213.00.010.031.03
and incl799011122.123.80.0140.052.05
UKHM22-0159.5112.55326.720.20.010.060.07
High-Grade Intervals
HoleFrom (m)To(m)Length (m)Ag Eq1(g/t)Ag(g/t)Au (g/t)Pb(%)Zn (%)
FOX22-0113.9514.450.5466.5206.00.021.124.81
and38.5739.070.5361.2115.00.010.684.85
and73.8479.75.86151.345.10.060.111.90
and121.51220.5488.955.00.000.139.34
FOX22-0232.5330.5806.9555.00.013.243.14
and158.08158.580.5315.343.00.010.045.76
and174.81175.50.69281.022.00.000.035.61
FOX22-0329.5530.140.59764.0463.00.230.795.41
and34.3134.810.5582.2316.00.081.394.57
and50.150.730.63657.1207.00.100.299.33
and99.53100.530.5740.177.00.030.0114.52
and153.85154.350.5817.4656.00.001.422.50
FOX22-0428.929.40.5294.1133.00.120.073.16
and53.49540.51355.7140.00.140.663.91
and67.48680.52846.7109.00.100.1615.75
and114.35114.850.5555.643.00.020.0111.02
FOX22-0527.9628.460.5558.4171.00.110.198.01
FOX22-0640.5410.5397.5134.00.3610.444.96
and80.686.35.7132.214.40.0160.022.46
Incl85.886.30.5526.958.00.0190.107.02
and1141151337.0110.00.030.194.70
UKHM22-0159.5600.5989.6763.00.322.182.59
and107.3107.850.551087.0953.00.023.560.28
Z222-0169.972.52.679.645.10.000.290.49
and129.51300.5222.7182.00.021.100.03

Notes to reported values:

  1. Ag equivalent is presented for comparative purposes using conservative long-term metal prices (all USD): $20/oz silver (Ag), $1.00/lb lead (Pb), $1.40/lb zinc (Zn).
  2. Recovered Silver Equivalent in Table 1 is determined as follows: Ag Eq g/t = [Ag g/t x recovery] + [Au g/t x recovery x Au price/ Ag price] + [Pb % x 10,000 x recovery x Pb price / Ag price] + [Zn% x 10,000 x recovery x Zn price / Ag price].
  3. In the above calculations: 1% = 10,000 ppm = 10,000 g/t.
  4. The following recoveries have been assumed for purposes of the above equivalent calculations: 95% for precious metals (Ag/Au) and 90% for all other listed metals, based on recoveries at similar nearby operations.
  5. Intervals are reported as measured drill intersect length.

Figure 2 – East Keno and Greater Fox target area with 2022 drill results and composite grade thickness values (Ag Eq1)

Metallic Minerals Corp., Thursday, January 12, 2023, Press release picture
Metallic Minerals Corp., Thursday, January 12, 2023, Press release picture

About Metallic Minerals

Metallic Minerals Corp. is an exploration and development stage company, focused on silver, gold and copper in the high-grade Keno Hill and La Plata mining districts of North America. Our objective is to create shareholder value through a systematic, entrepreneurial approach to making exploration discoveries, growing resources and advancing projects toward development. Metallic Minerals has consolidated the second-largest land position in the historic Keno Hill silver district of Canada’s Yukon Territory, directly adjacent Hecla Mining’s operations, with more than 300 million ounces of high-grade silver in past production and current M&I resources. Hecla Mining Company, the largest primary silver producer in the USA and third largest in the world, completed the acquisition of Alexco in September 2022. In April 2022, Metallic announced the inaugural NI 43-101 mineral resource estimate for its La Plata silver-gold-copper project in southwestern Colorado. The Company also continues to add new production royalty leases on its holdings in the Klondike gold district in the Yukon. All three districts have seen significant mineral production and have existing infrastructure, including power and road access. Metallic Minerals is led by a team with a track record of discovery and exploration success on several major precious and base metal deposits, as well as having large-scale development, permitting and project financing expertise.

FOR FURTHER INFORMATION, PLEASE CONTACT:

Website: www.mmgsilver.com Phone: 604-629-7800

Email: cackerman@mmgsilver.com Toll Free: 1-888-570-4420

Qualified Person

The disclosure in this news release of scientific and technical information regarding exploration projects on Metallic Minerals’ mineral properties has been reviewed and approved by Debbie James, Senior Geologist for TruePoint Exploration, who is a Qualified Person as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”).

Quality Assurance / Quality Control

All samples were assayed by 36 Element Aqua Regia Digestion ICP-MS methods at Bureau Veritas labs in Vancouver with sample preparation in Whitehorse, Yukon and geochemical analysis in Vancouver, British Columbia. Samples with over limit silver and gold were re-analyzed using a 30-gram fire assay fusion with a gravimetric finish. Over-limit lead and zinc samples were analyzed by multi-acid digestion and atomic absorption spectrometry. All results have passed the QAQC screening by the lab and the company utilized a quality control and quality assurance protocol for the project, including blank, duplicate, and standard reference samples.

Forward-Looking Statements

This news release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the company are forward-looking statements that involve various risks and uncertainties. Although Metallic Minerals believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Group Ten and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Metallic Minerals Corp.



View source version on accesswire.com:
https://www.accesswire.com/735000/Metallic-Minerals-Intercepts-1445-Meters-of-414-gt-Ag-Eq-as-Bulk-Tonnage-Ag-Pb-Zn-Zone-Emerges-as-Resource-Target-at-Fox-in-East-Keno-Keno-Silver-Project-Yukon-Canada

Categories
Base Metals Energy Granite Creek Copper Metallic Group Precious Metals

Granite Creek Copper Reports on Metallurgical Results in Support of an Updated PEA on the Carmacks Copper-Gold Project in Yukon, Canada

Granite Creek Copper, Proven and Probable

VANCOUVER, BC / ACCESSWIRE / January 10, 2023 / Granite Creek Copper Ltd. (TSXV:GCX | OTCQB:GCXXF) (“Granite Creek” or the “Company“)is pleased to report positive metallurgical results in support of the upcoming Preliminary Economic Assessment (“PEA”) for the Carmacks copper-gold-silver project (“the Project” or “Carmacks Project”) located in the Minto copper district, within the traditional territories of the Little Salmon Carmacks First Nation and the Selkirk First Nation, Yukon Canada.

Metallurgical testing completed by SGS Vancouver Metallurgy (“SGS”) supports a simplified process consisting of froth flotation for the recovery of copper, gold and silver from both sulphide and oxide ores at Carmacks. These tests demonstrate outstanding recovery levels and concentrate grades in both the sulphide only and blended sulphide/oxide samples, which would be utilized by the mine. Testing was done on samples consisting of material in which copper was present primarily in oxide minerals, where the copper was present as primarily sulphide minerals, and samples that were a blend of oxide and sulphide minerals. Table 1 below highlights selected results from this testing:

Table 1 – Flotation Recovery and concentrate grade.

Recovery %Concentrate Grade
SampleCuAuAgCu %Au g/tAg g/t
Sulphide/Oxide blend182.070.168.640.110.6104
Sulphide Sample293.769.078.442.77.7117
Oxide Sample339.857.537.426.213.693
  1. Locked cycle flotation on blend sample consisting of 60% sulfide and 40% oxide.
  2. The sulphide ore assayed 0.92% Cu, 0.67% S, and 0.24 g/t Au. Gold and copper head grades calculated from the flotation test assays agreed well with the direct head assays.
  3. The oxide ore assayed, 0.60% Cu, 0.06% S, and 0.25-0.82 g/t Au indicating that nugget gold may exist. However, the gold head grade calculated from the flotation tests was consistently between 0.20 g/t to 0.23 g/t with an average of 0.21 g/t. Locked cycle testing was not completed on the oxide samples.

Test work produced a very clean, premium, high-grade concentrate that forms the metallurgical basis for the process flow sheet of the PEA, which the company expects to publish by the end of the current quarter. Flotation optimization and an economic evaluation of the target copper grade versus recovery has been recommended by SGS and will be considered in future test work.

President and CEO, Tim Johnson, stated, “Building on the success of sulphide flotation testing completed in 2021, this study directly supports the PEA allowing a simplified flow sheet consisting of well-established froth flotation technology to be considered for increased overall recoveries at the Carmacks Project. Metallurgy is a key component of the upcoming PEA and with this important work complete we look forward to delivering the updated study to the market within the current quarter.”

Options

Granite Creek also announces that, subject to TSX Venture Exchange approval, it has granted 1,250,000 incentive stock options to directors, officers, employees, and consultants of the Company, under its long-term incentive plan. The options are exercisable for up to five years, expiring on January 10th, 2028 and each option will allow the holder to purchase one common share of the Company at a price of $0.08 per share.

About Granite Creek Copper

Granite Creek, a member of the Metallic Group of Companies, is a Canadian exploration company focused on the 176 square kilometer Carmacks project in the Minto copper district of Canada’s Yukon Territory. The project is on trend with the high-grade Minto copper-gold mine, operated by Minto Metals Corp., to the north, and features excellent access to infrastructure with the nearby paved Yukon Highway 2, along with grid power within 12 km. More information about Granite Creek Copper can be viewed on the Company’s website at www.gcxcopper.com.

FOR FURTHER INFORMATION PLEASE CONTACT:

Timothy Johnson, President & CEO
Telephone: 1 (604) 235-1982
Toll-Free: 1 (888) 361-3494
E-mail: info@gcxcopper.com
Website: www.gcxcopper.com
Twitter: @yukoncopper

Qualified Persons

Ms. Debbie James, P.Geo., a qualified person for the purposes of National Instrument 43-101, has reviewed and approved the technical disclosure contained in this news release. Ms. James is a Senior Geologist with TruePoint Exploration and a Project Manager at Carmacks.

Forward-Looking Statements

This news release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the company are forward-looking statements that involve various risks and uncertainties. Although Granite Creek Copper believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Granite Creek Copper and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Granite Creek Copper Ltd.

Categories
Emx Royalty Energy Junior Mining Metallic Group MillRock Resources Precious Metals Silver Bullet Mines Stillwater Critical Minerals

Platinum price on pace for 20% quarterly gain, its biggest since 2008

Platinum price on pace for 20% quarterly gain, its biggest since 2008

Stock image.

Due to ongoing supply concerns, platinum prices have surged more than 20% over the past three months, and the precious metal is now set to experience its best quarter since the start of 2009.

On Friday, platinum prices rose another 1.0% to $1,064.50 per ounce, bringing its quarterly gain to just under 23%.

SIGN UP FOR THE PRECIOUS METALS DIGEST

SIGN UP

Should the price of platinum maintain its 20% uptick, then this will will be the biggest quarterly increase since the first quarter of 2008, when it gained a staggering 34%.

According to the World Platinum Investment Council, top consumer China has imported excessive amounts of platinum metal since 2019, which has left a limited above-ground supply for the rest of the world.

“This, in combination with higher prices likely being needed to release Chinese inventories to the domestic market, could have a significant bearing on platinum market price discovery,” the Council wrote in its Platinum Perspectives report in December.

The Council is anticipating a platinum deficit in 2023, with demand growing by 19% while supply increasing by just 2%.

“Despite international economic turbulence, with many countries already in, or expected to tip into, recession, industrial demand for platinum will be up 10% compared to 2022, which exceeds the 10-year average,” the WPIC said in a press release.

Demand for platinum in the automotive industry will also continue to grow next year, while jewelry-based demand for platinum is forecasted to remain constant throughout 2023, the WPIC added.

According to Reuters data, platinum is by far the best-performing precious metal in 2022, recording a year-to-date gain of 9%. Over the same period, gold has lost around 1%, silver up around 3% and palladium down 4%.

(With files from Reuters)

Source: https://www.mining.com/platinum-price-on-pace-for-20-quarterly-gain-its-biggest-since-2008/

Categories
Base Metals Energy Granite Creek Copper Junior Mining Metallic Group Precious Metals

CORRECTING AND REPLACING: Granite Creek Copper Identifies New, High-Priority Resource Expansion Targets at Carmacks Copper-Gold-Silver Project in Yukon Canada

This press release corrects, replaces and entirely supersedes the prior version published on November 21, 2022 at 4:00 PM ET

VANCOUVER, BC / ACCESSWIRE / November 22, 2022 / Granite Creek Copper Ltd. (TSXV:GCX)(OTCQB:GCXXF) (“Granite Creek” or the “Company“) is pleased to announce results from an Induced Polarization (“IP”) survey conducted on the Company’s 100%-owned Carmacks copper-gold-silver project (“Carmacks” or the “Deposit”) in the Minto Copper District of central Yukon, Canada. The large, highly prospective, potential resource expansion targets identified adjacent to or near the proposed open pits warrant follow-up exploration in upcoming campaigns. The Company further announces it has closed the second and final tranche of the private placement financing described in a news release dated October 5, 2022.

President & CEO, Tim Johnson, stated, “These multiple new zones and targets adjacent to the conceptual open pits, as defined by the March NI 43-101 Mineral Resource Estimate update, further highlight the prospectivity of our Carmacks project. Our team continues to do excellent work at Carmacks and we are confident in our ability to expand known mineralization and make new discoveries in the lesser explored parts of the 176km2 project. The current focus is the completion of the upcoming PEA and we look forward to reporting on the robust economics of the Carmacks project in the near term.”

Survey Overview

The first survey line (Line 1100S) was conducted over Zone 147 to investigate the correlation between known copper sulphide mineralization and the chargeability response from the Simcoe Geophysics deep-penetrating IP survey (see Figure 2 below). Subsequent survey lines were conducted over near-deposit target areas.

The results of the survey were enhanced by Resistivity Scaled Chargeability (“RSC”). RSC is a ratio of chargeability to resistivity (electrical properties measured by the IP survey) with the applied ratio determined by comparing various ratios to known mineralized bodies. The well-defined Zone 147 was used as a model to determine the RSC ratio that best fit the known mineralization. (See Figure 4 below).

Figure 1 – Carmacks Copper-Gold Project Location

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Figure 2 – Location of 2022 Simcoe IP Lines

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Select Results

Line 1100S, surveyed over defined sulfide copper mineralization in Zone 147, established a model for the RSC response and identified a new zone ~920 meters to the west. This new zone, named the Sourtoe Zone, extends 200m south to Line 1300S. This zone has been investigated with soil samples and trenching, exposing visually mineralized material close to surface (results pending). The soils and trenching were designed to evaluate the geochemical and geological signatures of this near-surface IP response and their similarities to known mineralized zones.

Figure 3 – 2022 IP Survey Line 1100S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Line 1300S shows a potential continuation of the Sourtoe Zone, giving the zone a minimum of 200m strike length as well as a new, deeper target, the 147 Deep Target, several hundred meters below the proposed 147 pit.

Figure 4 – 2022 IP Survey Line 1300S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Line 1500S, designed to test the gap area between zones 2000 and 147 (the “Gap Zone”), was successful in identifying a significant anomaly that is offset to the west from both zones. 3D modeling of historic drilling shows that this target has not been drill tested and could represent a southern extension of the 147 zone. The Gap Zone Target is a top candidate for additional near-deposit exploration (See figure 4). Additionally, a new, deeper target area that appears on this line and extends to line 1700S has been identified as the 58 Target.

Figure 5 – 2022 IP Survey Line 1500S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Line 1700S, located 200m south of Line 1500S, shows the probable Gap Zone Target continuing southwards towards Zone 2000 as well as the newly identified 58 Target. Additionally, a shallow anomaly east of the proposed pit is identified as a possible continuation of Zone 4 proximal to the 147 pit.

Figure 6 – 2022 IP Survey Line 1700S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Line 3300S, the southern most line completed in this survey highlights the potentiality of the area underneath the proposed 1213 pit. Additionally, an anomaly on the western portion of the line has been identified as 1213 west target for further follow up. With the current pit design bottoming out at 180 meters there remains significant room to grow the resource in this area. Additional lines on 200m spacing over the 1213 area are planned for subsequent geophysical campaigns to further define the zone.

Figure 7 – 2022 IP Survey Line 3300S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

To view the full sized image (Click Here)

Closing of Second Tranche of Private Placement

The Company announces the completion of the second tranche of the previously announced private placement offering (the “Offering”) which has raised aggregate proceeds of $148,700 through the issuance of a total of 1,142,667 non-flow-through units and 572,727 flow-through shares (the “Offering”). The Offering remains subject to the final approval of the TSX Venture Exchange.

The Company issued an aggregate of 1,933,273 flow-through shares (“FT shares”) at a price of $0.11 per share, to raise proceeds of $212,660.03 to incur Canadian Exploration Expenses (“CEE”) under the Income Tax Act (Canada). The Company raised a further $193,799.93 through the issuance of 2,583,999 non flow-through units at a price of $0.075 with each unit consisting of one common share of the Company and one warrant (a “Warrant”), with each Warrant allowing the holder to purchase one common share of the Company at a price of $0.10 per share for twenty-four months from the Closing Date of the Offering.

All shares issued under the Offering are subject to a hold period of four months and one day from issuance in accordance with applicable securities laws and the policies of the TSX Venture Exchange. The Shares have not been, and will not be, registered under the U.S. Securities Act or any U.S. state securities laws and may not be offered or sold in the United States or to, or for the account or benefit of, U.S. persons, absent registration or any applicable exemption from the registration requirements of the U.S. Securities Act and applicable U.S. state securities laws. The Offering remains subject to the final approval of the TSX Venture Exchange.

The Company has agreed to pay finders’ fees totalling of $13,259 in cash or shares on a portion of the Private Placement and to issue 127,042 finder warrants. Each finder warrant is exercisable into one common share of the Company at a price of $0.10 per share for a period of 24 months from the date of closing.

The Offering constitutes a related party transaction within the meaning of Multilateral Instrument 61-101 – Protection of Minority Security Holders in Special Transactions (“MI 61-101”), as insiders of the Company subscribed for an aggregate of 600,001 units for proceeds of $48,500.08. The Company relied on the exemptions in Section 5.5(b) – Issuer Not Listed on Specified Markets from the formal valuation requirements of MI 61-101 and relied on the exemption in Section 5.7(1)(a) – Fair Market Value Not More Than 25 Per Cent of Market Capitalization from the minority shareholder approval requirements of MI 61-101. The Company did not file a material change report at least 21 days before the expected closing date of the Offering as the aforementioned insider participation had not been confirmed at that time and the Company wished to close the Offering as expeditiously as possible.

Qualified Persons

Ms. Debbie James, P.Geo., a qualified person for the purposes of National Instrument 43-101, has reviewed and approved the technical disclosure contained in this news release. Ms. James is a Senior Geologist with TruePoint Exploration and a Project Manager at Carmacks.

About Granite Creek Copper

Granite Creek, a member of the Metallic Group of Companies, is a Canadian exploration company focused on the 176km2 Carmacks project in the Minto copper district of Canada’s Yukon Territory. The project hosts a National Instrument 43-101 compliant mineral resource estimate consisting of 36.2 million tonnes grading 0.81% Cu, 0.31 g/t Au and 3.41 g/t Ag on trend with Minto Metals’ high-grade Minto copper-gold mine and features excellent access to infrastructure with the nearby paved Yukon Highway 2, along with grid power within 12 km. More information about Granite Creek Copper can be viewed on the Company’s website at www.gcxcopper.com.

FOR FURTHER INFORMATION PLEASE CONTACT:

Timothy Johnson, President & CEO
Telephone: 1 (604) 235-1982
Toll-Free: 1 (888) 361-3494
E-mail: info@gcxcopper.com
Website: www.gcxcopper.com
Twitter: @yukoncopper

Forward-Looking Statements

This news release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the company are forward-looking statements that involve various risks and uncertainties. Although Granite Creek Copper believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Granite Creek Copper and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Granite Creek Copper Ltd.



View source version on accesswire.com:
https://www.accesswire.com/727695/CORRECTING-AND-REPLACING-Granite-Creek-Copper-Identifies-New-High-Priority-Resource-Expansion-Targets-at-Carmacks-Copper-Gold-Silver-Project-in-Yukon-Canada

Categories
Base Metals Energy Granite Creek Copper Junior Mining Metallic Group

Granite Creek Copper Identifies New, High-Priority Resource Expansion Targets at Carmacks Copper-Gold-Silver Project in Yukon Canada

VANCOUVER, BC / ACCESSWIRE / November 21, 2022 / Granite Creek Copper Ltd. (TSXV:GCX | OTCQB:GCXXF) (“Granite Creek” or the “Company“) is pleased to announce results from an Induced Polarization (“IP”) survey conducted on the Company’s 100%-owned Carmacks copper-gold-silver project (“Carmacks” or the “Deposit”) in the Minto Copper District of central Yukon, Canada. The large, highly prospective, potential resource expansion targets identified adjacent to or near the proposed open pits warrant follow-up exploration in upcoming campaigns. The Company further announces it has closed the second and final tranche of the private placement financing described in a news release dated October 5, 2022.

President & CEO, Tim Johnson, stated, “These multiple new zones and targets adjacent to the conceptual open pits, as defined by the March NI 43-101 Mineral Resource Estimate update, further highlight the prospectivity of our Carmacks project. Our team continues to do excellent work at Carmacks and we are confident in our ability to expand known mineralization and make new discoveries in the lesser explored parts of the 176km2 project. The current focus is the completion of the upcoming PEA and we look forward to reporting on the robust economics of the Carmacks project in the near term.”

Survey Overview

The first survey line (Line 1100S) was conducted over Zone 147 to investigate the correlation between known copper sulphide mineralization and the chargeability response from the Simcoe Geophysics deep-penetrating IP survey (see Figure 2 below). Subsequent survey lines were conducted over near-deposit target areas.

The results of the survey were enhanced by Resistivity Scaled Chargeability (“RSC”). RSC is a ratio of chargeability to resistivity (electrical properties measured by the IP survey) with the applied ratio determined by comparing various ratios to known mineralized bodies. The well-defined Zone 147 was used as a model to determine the RSC ratio that best fit the known mineralization. (See Figure 4 below).

Figure 1 – Carmacks Copper-Gold Project Location

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Figure 2 – Location of 2022 Simcoe IP Lines

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Select Results

Line 1100S, surveyed over defined sulfide copper mineralization in Zone 147, established a model for the RSC response and identified a new zone ~920 meters to the west. This new zone, named the Sourtoe Zone, extends 200m south to Line 1300S. This zone has been investigated with soil samples and trenching, exposing visually mineralized material close to surface (results pending). The soils and trenching were designed to evaluate the geochemical and geological signatures of this near-surface IP response and their similarities to known mineralized zones.

Figure 3 – 2022 IP Survey Line 1100S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Line 1300S shows a potential continuation of the Sourtoe Zone, giving the zone a minimum of 200m strike length as well as a new, deeper target, the 147 Deep Target, several hundred meters below the proposed 147 pit.

Figure 4 – 2022 IP Survey Line 1300S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Line 1500S, designed to test the gap area between zones 2000 and 147 (the “Gap Zone”), was successful in identifying a significant anomaly that is offset to the west from both zones. 3D modeling of historic drilling shows that this target has not been drill tested and could represent a southern extension of the 147 zone. The Gap Zone Target is a top candidate for additional near-deposit exploration (See figure 4). Additionally, a new, deeper target area that appears on this line and extends to line 1700S has been identified as the 58 Target.

Figure 5 – 2022 IP Survey Line 1500S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Line 1700S, located 200m south of Line 1500S, shows the probable Gap Zone Target continuing southwards towards Zone 2000 as well as the newly identified 58 Target. Additionally, a shallow anomaly east of the proposed pit is identified as a possible continuation of Zone 4 proximal to the 147 pit.

Figure 6 – 2022 IP Survey Line 1700S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Line 3300S, the southern most line completed in this survey highlights the potentiality of the area underneath the proposed 1213 pit. Additionally, an anomaly on the western portion of the line has been identified as 1213 west target for further follow up. With the current pit design bottoming out at 180 meters there remains significant room to grow the resource in this area. Additional lines on 200m spacing over the 1213 area are planned for subsequent geophysical campaigns to further define the zone.

Figure 7 – 2022 IP Survey Line 3300S

Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture
Granite Creek Copper Ltd., Monday, November 21, 2022, Press release picture

Closing of Second Tranche of Private Placement

The Company announces the completion of the previously announced private placement offering which has raised aggregate proceeds of $148,700 through the issuance of a total of 1,142,667 non-flow-through units and 572,727 flow-through shares (the “Offering”). The Offering remains subject to the final approval of the TSX Venture Exchange.

The Company issued XX flow-through shares (“FT shares”) at a price of $0.11 per share, to raise proceeds of $XX to incur Canadian Exploration Expenses (“CEE”) under the Income Tax Act (Canada). The Company issued a total of XX units at a price of $0.075 with each unit consisting of one common share of the Company and one warrant (a “Warrant”), with each Warrant allowing the holder to purchase one common share of the Company at a price of $0.10 per share for twenty-four months from the Closing Date of the Offering.

The Shares are subject to a hold period of four months and one day from issuance in accordance with applicable securities laws and the policies of the TSX Venture Exchange. The Shares have not been, and will not be, regis-tered under the U.S. Securities Act or any U.S. state securities laws and may not be offered or sold in the United States or to, or for the account or benefit of, U.S. persons, absent registration or any applicable exemption from the registration requirements of the U.S. Securities Act and applicable U.S. state securities laws.

The Company has agreed to pay finders’ fees totalling of $13,259 in cash or shares on a portion of the Private Placement and to issue 127,042 finder warrants. Each finder warrant is exercisable into one common share of the Company at a price of $0.10 per share for a period of 24 months from the date of closing.

The Offering constitutes a related party transaction within the meaning of Multilateral Instrument 61-101 – Protection of Minority Security Holders in Special Transactions (“MI 61-101”), as insiders of the Company subscribed for an aggregate of 600,001 units for proceeds of $48,500.08. The Company relied on the exemptions in Section 5.5(b) – Issuer Not Listed on Specified Markets from the formal valuation requirements of MI 61-101 and relied on the exemption in Section 5.7(1)(a) – Fair Market Value Not More Than 25 Per Cent of Market Capitalization from the minority shareholder approval requirements of MI 61-101. The Company did not file a material change report at least 21 days before the expected closing date of the Offering as the aforementioned insider participation had not been confirmed at that time and the Company wished to close the Offering as expeditiously as possible.

Qualified Persons

Ms. Debbie James, P.Geo., a qualified person for the purposes of National Instrument 43-101, has reviewed and approved the technical disclosure contained in this news release. Ms. James is a Senior Geologist with TruePoint Exploration and a Project Manager at Carmacks.

About Granite Creek Copper

Granite Creek, a member of the Metallic Group of Companies, is a Canadian exploration company focused on the 176km2 Carmacks project in the Minto copper district of Canada’s Yukon Territory. The project hosts a National Instrument 43-101 compliant mineral resource estimate consisting of 36.2 million tonnes grading 0.81% Cu, 0.31 g/t Au and 3.41 g/t Ag on trend with Minto Metals’ high-grade Minto copper-gold mine and features excellent access to infrastructure with the nearby paved Yukon Highway 2, along with grid power within 12 km. More information about Granite Creek Copper can be viewed on the Company’s website at www.gcxcopper.com.

FOR FURTHER INFORMATION PLEASE CONTACT:

Timothy Johnson, President & CEO

Telephone: 1 (604) 235-1982
Toll-Free: 1 (888) 361-3494
E-mail: info@gcxcopper.com
Website: www.gcxcopper.com
Twitter: @yukoncopper

Forward-Looking Statements

This news release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the company are forward-looking statements that involve various risks and uncertainties. Although Granite Creek Copper believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Granite Creek Copper and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Granite Creek Copper Ltd.



View source version on accesswire.com:
https://www.accesswire.com/727608/Granite-Creek-Copper-Identifies-New-High-Priority-Resource-Expansion-Targets-at-Carmacks-Copper-Gold-Silver-Project-in-Yukon-Canada

Categories
Base Metals Energy Junior Mining Metallic Group Metallic Minerals Precious Metals

Metallic Minerals Acquires Additional Claims at La Plata Copper-Silver-Gold Project in Colorado, USA

VANCOUVER, BC / ACCESSWIRE / November 10, 2022 / Metallic Minerals Corp. (TSXV:MMG)(OTCQB:MMNGF) (“Metallic Minerals” or the “Company”) is pleased to announce that it has acquired a 100% interest in six (6) patented mineral claims (78.2 acres), known as the Morning Star property, within the La Plata mining district of southwestern Colorado. The claims are surrounded by, and contiguous with, unpatented mining claims held by the Company within the greater La Plata property claim outline, which now totals over 33 square kilometers (km2) in size. The Morning Star claims have the potential to host porphyry-style Cu-Ag-Au mineralization as both an extension of the nearby Allard resource or as a new porphyry center. In addition, the claims host potential for high-grade Au-Ag-Te epithermal mineralization.

Morning Star Property Highlights

The 78.2-acre Morning Star property consists of six (6) federally patented mining claims that include both fee simple surface ownership and sub-surface mineral rights. The claims straddle the Montezuma and La Plata County boundary and have the potential to host both porphyry Cu-Ag-Au mineralization, as well as epithermal style deposits of high-grade gold, silver, and tellurium, a critical metal on the United States Geological Survey’s list of 50 mineral commodities critical to the U.S. economy and national security2. While highly prospective, the acquired property has not seen modern exploration work in recent decades but was patented in the early 1900s, based on the discovery of significant surface mineralization.

Metallic Minerals Corp., Wednesday, November 9, 2022, Press release picture
Metallic Minerals Corp., Wednesday, November 9, 2022, Press release picture

Transaction Details

Subject to final TSX approval, Metallic Minerals will acquire a 100% interest in the Morning Star property for a one-time cash payment totaling US$35,000 and the issuance of an aggregate of 275,000 common shares of Metallic Minerals following regulatory approval.

Scott Petsel, Metallic Minerals President stated, “We are pleased to be able to acquire these additional claims in the highly prospective La Plata mining district, where we recently announced an inferred resource of 985 million pounds of copper equivalent at the Allard Deposit1, which represents just one of several significant porphyry target areas on the property. This acquisition comes on the heels of the recently completed 2022 field program, which focused on resource expansion drilling at the Allard Deposit and included property-wide ground-based induced polarization and resistivity geophysical surveys. Along with the results from the 2022 La Plata drill program and field work, which are expected to come in over the next couple of months, these newly acquired claims will be incorporated into the development of our 2023 exploration season plans and targeting.”

“Assay results from the Keno Silver Project on over 3,200 meters of drilling focused on resource definition at several resource ready targets are expected in the coming weeks.”

About La Plata Silver-Gold-Copper Project

The road accessible La Plata project covers 33 km2 approximately 10 km northeast of the town of Mancos, Colorado within the historic high-grade La Plata mining district, located at the southwest end of the prolific Colorado Mineral Belt. Mineralization is related to a large-scale precious-metals-rich porphyry copper system with associated high-grade silver and gold epithermal vein and replacement deposits.

The La Plata district has a long and rich history of mining with the first silver deposits discovered in the 1700s by Spanish explorers. High-grade silver and gold production has been documented from the 1870s through the early 1940s from vein structures, replacement bodies and breccia zones at over 90 individual mines and prospects3. Historical production from some of these high-grade structures exceeded 1,000 grams per tonne (“g/t”) silver and over 15 g/t gold with some of the richest deposits delivering true bonanza grades for silver and gold.

From the 1950s to 1970s, major miners including Rio Tinto (Bear Creek) and Freeport-McMoRan (Phelps Dodge) explored in the La Plata district focusing on the significant potential for bulk-tonnage disseminated and stockwork hosted mineralization. Freeport-McMoRan retained ownership of claims in the district until 2002 when they sold their holdings to the current underlying vendors during the lows of the last metal price cycle.

Prior to 2022, a total of 56 drill holes, totaling 15,200 m, have been drilled on the property since the 1950s which confirms the presence of a large-scale, multi-phase porphyry system with significant silver, gold and copper that is associated with a 10 km2 strongly magnetic signature with intense hydrothermal alteration.

The April 2022 NI 43-101 Mineral Resource Estimate, which covers a relatively small part of the overall 33 km2 property, consists of 115.7 million tonnes at an average grade of 0.39% copper equivalent (“Cu Eq”) (0.35% Cu and 4.02 g/t Ag) using a 0.25% Cu Eq cut-off grade1. The deposit is steeply dipping and roughly tabular in shape, occurring over 1 km in length, 400 m in width with over 1 km in vertical extent based on drilling to date. The Allard deposit remains open to expansion in all directions.

The Allard deposit is a significant potential source of copper and silver, both important metals for the modernization and electrification of the economy. In addition, the broader La Plata property is known for the occurrence of important critical minerals that have been identified by the US Government as essential for the functioning of modern technologies and economies and that are at risk of supply disruption2. The resampling of hole 95-1 during the 2021 field season returned significant platinum and palladium assays associated with the Copper Hill target area east of the Allard resource area and corroborated historic accounts of its presence. Tellurium, another element on the critical mineral list, was a by-product of historic high-grade gold and silver production in the district. These and other important metals noted in the district will be evaluated as part of ongoing exploration of the project.

Upcoming Events

Yukon Geoscience

Metallic Minerals will be attending the annual Yukon Geoscience event in Whitehorse, Yukon November 19-22, with geologist, Taylor Haid, scheduled to give a technical presentation on the Keno Silver project.

Mines & Money London

Metallic Minerals President, Scott Petsel, will be attending the Mines & Money one-one-one conference in London, England November 29-December first, with meetings now being booked.

Footnotes

1) See Technical Report on the Inaugural Mineral Resource Estimate for the Allard Cu-Ag Porphyry Deposit, La Plata Project, Colorado, USA with an effective date of April 3, 2022. The Mineral Resource, prepared by Allan Armitage P. Geo of SGS Geological Services, an independent Qualified Person, has been estimated in conformity with CIM Estimation of Mineral Resource and Mineral Reserve Best Practices Guidelines (2019) and current CIM Definition Standards – For Mineral Resources and Mineral Reserves (2014). The constrained Mineral Resources are reported at a base case cut-off grade of 0.25% CuEq, based on metal prices of $3.60/lb Cu and $22.50/oz Ag, assumed metal recoveries of 90% for Cu and 65% for Ag, a mining cost of US$5.30/t rock and processing and G&A cost of US$11.50/t mineralized material. Copper Equivalent (Cu Eq) calculations are included for comparative purposes. The current Mineral Resources are not Mineral Reserves as they do not have demonstrated economic viability. The quantity and grade of reported Inferred Resources in this Mineral Resource Estimate are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as Indicated or Measured. However, based on the current knowledge of the deposits, it is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.

2) The US Geological Survey has released a list of 50 critical minerals that the US economy requires for economic and national security.

3) Eckel, USGS Prof Paper 219, Geology and Ore Deposits of the La Plata Mining District, 1949.

Qualified Person

Jeff Cary, CPG, a qualified person for the purposes of National Instrument 43-101, has reviewed and approved the technical disclosure contained in this news release. Mr. Cary is a Senior Geologist and La Plata Project Manager for Metallic Minerals.

About Metallic Minerals

Metallic Minerals Corp. is an exploration and development stage company, focused on silver, gold and copper in the high-grade Keno Hill and La Plata mining districts of North America. Our objective is to create shareholder value through a systematic, entrepreneurial approach to making exploration discoveries, growing resources and advancing projects toward development. Metallic Minerals has consolidated the second-largest land position in the historic Keno Hill silver district of Canada’s Yukon Territory, directly adjacent Hecla Mining’s operations, with more than 300 million ounces of high-grade silver in past production and current M&I resources. Hecla Mining Company, the largest primary silver producer in the USA and third largest in the world, completed the acquisition of Alexco in September 2022. In April 2022, Metallic announced the inaugural NI 43-101 mineral resource estimate for its La Plata silver-gold-copper project in southwestern Colorado. The Company also continues to add new production royalty leases on its holdings in the Klondike gold district in the Yukon. All three districts have seen significant mineral production and have existing infrastructure, including power and road access. Metallic Minerals is led by a team with a track record of discovery and exploration success on several major precious and base metal deposits, as well as having large-scale development, permitting and project financing expertise.

FOR FURTHER INFORMATION, PLEASE CONTACT:

Website: www.mmgsilver.com
Email: cackerman@mmgsilver.com
Phone: 604-629-7800
Toll Free: 1-888-570-4420

Forward-Looking Statements

This news release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the company are forward-looking statements that involve various risks and uncertainties. Although Metallic Minerals believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Group Ten and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Metallic Minerals Corp.

Categories
Base Metals Energy Junior Mining Metallic Group Metallic Minerals Precious Metals

Stillwater Critical Minerals Applies for Warrant Extension

VANCOUVER, BC / ACCESSWIRE / November 4, 2022 / Stillwater Critical Minerals (formerly Group Ten Metals) (TSXV:PGE)(OTCQB:PGEZF)(FSE:5D32) (the “Company” or “SWCM”) announces that the Company has applied for TSX Venture Exchange approval to extend the expiry date on certain warrants that were due to expire November 21, 2022 (the “Warrants”). Per the application, 5,233,824 Warrants that were originally issued as part of a financing completed in November 2019 (see news release dated November 21, 2019) will be extended to a new expiration date of May 21, 2023. Each Warrant entitles the holder to acquire one common share at an exercise price of CDN$ 0.25.

About Stillwater Critical Minerals Corp.

Stillwater Critical Minerals (TSX.V: PGE | OTCQB: PGEZF) is a mineral exploration company focused on its flagship Stillwater West PGE-Ni-Cu-Co + Au project in the iconic and famously productive Stillwater mining district in Montana, USA. With the recent addition of two renowned Bushveld and Platreef geologists to the team, the Company is well positioned to advance the next phase of large-scale critical mineral supply from this world-class American district, building on past production of nickel, copper, and chromium, and the ongoing production of platinum group and other metals by neighboring Sibanye-Stillwater. The Platreef-style nickel and copper sulphide deposits at Stillwater West contain a compelling suite of critical minerals and are open for expansion along trend and at depth, with an updated NI 43-101 mineral resource update now in progress based on a 14-hole expansion drilling campaign.

Stillwater Critical Minerals also holds the high-grade Drayton-Black Lake Gold project adjacent to Treasury Metals’ development-stage Goliath Gold Complex in northwest Ontario. Drayton-Black Lake is currently under an earn-in agreement with an option to joint venture whereby Heritage Mining may earn up to a 90% interest in the project by completing payments and work on the project. The Company also holds the Kluane PGE-Ni-Cu-Co project on trend with Nickel Creek Platinum‘s Wellgreen deposit in Canada‘s Yukon Territory.

FOR FURTHER INFORMATION, PLEASE CONTACT:

Michael Rowley, President, CEO & Director
Email: info@criticalminerals.com
Phone: (604) 357 4790
Web: http://criticalminerals.com
Toll Free: (888) 432 0075

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Stillwater Critical Minerals Corp.



View source version on accesswire.com:
https://www.accesswire.com/724042/Stillwater-Critical-Minerals-Applies-for-Warrant-Extension