Categories
Base Metals Energy Junior Mining Nevada Copper

Nevada Copper Provides Update on Accelerating Stope Production and Ramp-Up Progress and Announces Appointment of Chief Executive Officer

YERINGTON, Nev., Oct. 06, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDD) (“Nevada Copper” or the “Company”) today provided a further update on positive September operational performance at the Company’s underground mine at its Pumpkin Hollow Project (the “Underground Mine”). In addition, the Company is pleased to announce the appointment of Randy Buffington as President and Chief Executive Officer, further strengthening its senior management team as operational productivity and production ramp-up at the Underground Mine.

September Operational Highlights

  • Higher Copper Production: Copper in concentrate produced during September increased by 265% compared to August driven by higher stope production. Approximately 30,386 tons of ore were processed yielding 682 tons of concentrate at an average grade of 22%, resulting in approximately 150 tons of copper production.
  • Improved rate of stope turnover: Stoping has accelerated significantly since mid-August, with the second and third stope panels fully mined and a fourth stope panel expected to be mined this week. Further stopes are planned in October and November, and the high-grade Sugar Cube zone is also expected to begin to be mined during Q4.
  • Increasing Development Rates: September saw the highest monthly development footage achieved since April 2021, with a 12% increase over August. Development activities included completion of the crossing of the water bearing dike, accessing additional stoping zones and installation of development infrastructure. A total of approximately 750 lateral equivalent feet was advanced in September.

Mike Brown, outgoing Interim President and Chief Executive Officer, commented: “I am very pleased to see the improved trajectory in our production ramp-up and a recovery in productivities. The increased ore production was a key objective for September, and together with the improving productivities on site, along with the ongoing management strengthening, provide further confidence in the mine ramp-up.”https://s.yimg.com/rq/darla/4-9-0/html/r-sf-flx.html

Management Update

Randy Buffington will join Nevada Copper as President and Chief Executive Officer with immediate effect. With extensive experience in underground and open pit mining operations, both in Nevada and internationally, Mr. Buffington has successfully delivered multiple project ramp-ups and productivity improvements in an underground setting, in addition to overseeing the development and operation of multiple large open pit projects. Most recently at Hycroft Mining, he was responsible for the operational reforms, successfully executing a project turnaround and delivering significant shareholder value as President and Chief Executive Officer. Previously, he held various senior management positions with Barrick from 2003 to 2012, overseeing North American and Zambian operations. He also held senior management positions with Placer Dome and Cominco.

Mr. Buffington brings a deep industry network in Nevada and a strong track record of value delivery in both operating underground mines and large open pit projects, ideally positioning him to lead Nevada Copper towards the delivery of steady state production from its Underground Mine and realizing the full potential of its fully-permitted open pit project and extensive landholdings within the Yerington Copper District.

“The addition of Mr. Buffington further strengthens the Company’s senior management team and provides deeply experienced, long-term leadership as the Company moves to complete the ramp-up of the Underground Mine and go on to maximize the full value of its open pit project and exploration targets,” stated Stephen Gill, Chairman of Nevada Copper.

“I look forward to working with the team at Nevada Copper as we continue to push and improve productivity and accelerate our transition into a commercial producer,” stated Randy Buffington, President and CEO of Nevada Copper. “There is a tremendous foundation to build on at Pumpkin Hollow and I am pleased to be leading the Company towards realizing its full potential as a mid-tier copper producer.”

Mike Brown will step down as Interim President and Chief Executive Officer and continue his active involvement and oversight through his ongoing role as director.

“On behalf of the Company, I would like to thank Mike Brown for his commitment as Interim President and Chief Executive Officer, and I look forward to his continued active involvement going forward,” stated Mr. Gill.

Qualified Persons
The technical information and data in this news release was reviewed by Greg French, C.P.G., VP Head of Exploration of Nevada Copper, and Neil Schunke, P.Eng., a consultant to Nevada Copper, who are both non-independent Qualified Persons within the meaning of NI 43-101.

About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.
www.nevadacopper.com
Randy Buffington, President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to mine development, production and ramp-up plans.

Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; failure to obtain extensions under and amendments to the Company’s amended and restated senior credit facility with KfW IPEX-Bank; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. The forward-looking information or statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.

Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Categories
Base Metals Energy Junior Mining Nevada Copper

Nevada Copper Announces Financing Update

YERINGTON, Nev., Oct. 01, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDD) (“Nevada Copper” or the “Company”) is pleased announce that the Company has received a further extension of the waiver from KfW IPEX-Bank (“KfW”), the Company’s senior project lender, to October 31, 2021 to complete the project completion test (the “Project Longstop Date”) under the Company’s amended and restated credit agreement (the “Amended KfW Facility”). As previously announced, the Company and KfW are in discussions regarding a longer-term extension of the Project Longstop Date. While there can be no assurance, the Company expects to enter into this longer-term extension and finalize certain other amendments, including payment deferrals, to the Amended KfW Facility by the end of October.

As a condition to the most recent waiver from KfW, Pala Investments Limited (“Pala”), the Company’s largest shareholder, will provide a new US$12 million loan to the Company pursuant to a promissory note entered into between Pala and the Company (the “Promissory Note”). The Promissory Note has substantially the same terms as the amended and restated promissory note issued by the Company in favour of Pala, as described in the Company’s August 31, 2021 press release, however, no arrangement fee is payable to Pala under the Promissory Note. The Promissory Note was reviewed and approved by a committee of independent directors of the Company.

Effective September 30, 2021, Justin Cochrane resigned from the Company’s board of directors (the “Board”) in order to focus on the other businesses that he’s involved with and to reduce the number of boards on which he sits.https://s.yimg.com/rq/darla/4-9-0/html/r-sf-flx.html

“On behalf of the Company, I would like to thank Justin Cochrane for his contributions to the Company and wish him success in his future endeavours,” stated Stephen Gill, Chairman of the Board.

About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.
www.nevadacopper.com
Mike Brown, Interim President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to an extension and amendments in connection with the Amended KfW Facility.

Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of its underground mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; failure to obtain extensions under and amendments to the Amended KfW Facility; ground conditions; cost overruns relating to development, construction and ramp-up of its underground mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. In particular, there can be no assurance that the extension and amendments to the Amended KfW Facility or the conditions for their effectiveness will be achieved at all or within the necessary timeframe, in which case the Company may have to cease operations in the absence of an alternative financing transaction. The forward-looking information or statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.

Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Categories
Base Metals Energy Junior Mining Nevada Copper

Nevada Copper Provides Operations Update

YERINGTON, Nev., Sept. 21, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF) (“Nevada Copper” or the “Company”) today provided an update on management team additions and execution of its productivity improvement plan.

Highlights

  • Accelerated stope turnover rates: The pace of stope mining continues to accelerate at the Company’s underground mine at its Pumpkin Hollow Project (the “Underground Mine”), with mining from the second stope already complete, and blasting of the third stope commenced. Further improved visibility on stoping inventory and additional stopes is planned in the coming weeks.
  • Team strengthened in key positions: Following Mike Brown assuming the role of Interim President and Chief Executive Officer, a number of key positions have been swiftly filled, adding key mining skills and building out the execution team. Key positions include GM Underground Projects, Interim Chief Operating Officer, Underground Production Manager, Process Manager, Senior Electrical Engineer, and Director of Financial Reporting.
  • Productivity improvement plan generating positive results: Management, including new team additions, have initiated a productivity improvement plan aimed at addressing the operational challenges at the Underground Mine encountered during Q2 2021, including improved planning, monitoring and contractor management systems. In the weeks since initiated, substantial improvements in productivity have been demonstrated in development rates.
  • Processing: Ore from stope mining averaging approximately 1.5% Cu is being delivered to the mill with recoveries as planned and production of concentrate meeting offtake specifications while batch processing ore.

Mike Brown, Interim President and Chief Executive Officer, commented: “I am very pleased to welcome the new additions to our team. Along with strengthened leadership and the addition of key skills, we are already seeing improvements in operational execution and productivity, resulting in increased stope turnover rates. These results are encouraging as we embed operational improvements and continue with the ramp-up of copper production”.

Further Details

Team Strengthening
During August and September, a number of key additions to the Pumpkin Hollow operating team have been made. These additions address prior limitations in availability of mining and geotechnical technical skills within the management team. Key among these additions are:

  • GM Underground Projects: Robert Booth will oversee all underground mining activities, including contractor management and infrastructure. Mr. Booth has substantial underground mining and contractor management experience in the Americas, including as Project Director for Hudbay Minerals since 2018, as Project Director and Mine Manager across Vale’s Canadian operations between 1990 and 2017, and prior to that at Inco Limited.
  • Interim Chief Operating Officer
  • Underground Production Manager
  • Process Manager
  • Senior electrical engineer
  • Director, financial reporting

Productivity Improvement Plan
Over recent weeks, management has undertaken a detailed review of the constraints encountered during Q2 2021 at the Underground Mine and reviewed planning for the remaining ramp-up and steady-state operations. As a result, a number of measures have been implemented to address operational constraints encountered in Q2, including:

  • Stronger contractor management procedures combined with revised contractor key performance indicators and aligned incentive systems to drive improved mining productivity.
  • Planning focus on accelerated stope delivery and prioritization of certain underground infrastructure items key to delivering higher production volumes.
  • Implementation of enhanced inventory management systems and supply chain optimization to ensure critical consumables and spares are available to service mining activities.
  • Optimization of equipment utilization, including revisions to the mobile equipment maintenance program.

The above measures are delivering operational improvements and providing greater visibility on stoping inventory. An increased rate of stope mining is underway with the second stopes mined, the blasting of the third stope having commenced and further stopes planned in the coming weeks.

The surface ventilation fans for the Underground Mine remain on schedule for commissioning in Q4 2021. The Company will provide further updates on operating performance metrics in due course.

Credit Facility Amendments
Discussions are progressing positively with KfW-IPEX Bank (“KfW”), in-line with the expectations previously reported in the Company’s August 31, 2021 news release. The Company expects to finalize amendments to its senior facility with KfW in the coming weeks in order to, among other things, extend the project completion longstop date under the facility. However, there can be no assurance that such amendments and extensions will be obtained.

Completion of Share Consolidation
The Company has completed the previously announced consolidation of its issued and outstanding common shares on the basis of one (1) post-consolidation common share for every ten (10) pre-consolidation common shares (the “Share Consolidation”). The common shares will begin trading on a post-consolidation basis at the market open on September 21, 2021. See the Company’s September 3, 2021 press release for additional details on the Share Consolidation.

Qualified Persons
The technical information and data in this news release was reviewed by Greg French, C.P.G., and Norm Bisson, P.Eng., for Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.

About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.
www.nevadacopper.com
Mike Brown, Interim President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to mine development plans, production and ramp-up plans and the expected timing and results thereof, equipment installation, and amendments to the Company’s amended and restated senior credit facility with KfW.

Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; failure to obtain extensions under and amendments to the Company’s amended and restated senior credit facility with KfW; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements and information. The forward-looking information and statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.

Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Categories
Base Metals Breaking Energy Junior Mining Nevada Copper

Nevada Copper Announces Effective Date of Share Consolidation

YERINGTON, Nev., Sept. 03, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF) (“Nevada Copper” or the “Company”) announces implementation of the 10:1 consolidation (the “Share Consolidation”) of the Company’s common shares (“Common Shares”), which was previously approved by the Company’s shareholders at the Company’s annual and special meeting of shareholders held on June 30, 2021 (the “Meeting”). The Toronto Stock Exchange (the “TSX”) has conditionally approved the Share Consolidation, subject to the filing of certain customary documents. The Share Consolidation will become effective on September 17, 2021 and the Common Shares are expected to commence trading on the TSX on a post-consolidation basis on or about September 21, 2021.

Following the Share Consolidation, the number of outstanding Common Shares will be reduced from approximately 1,850,635,602 outstanding Common Shares to approximately 185,063,560 outstanding Common Shares. The Common Shares will continue to be listed on the TSX under the symbol “NCU”. Following the Share Consolidation, the new CUSIP number for the Common Shares will be 64128F703 and the new ISIN for the Common Shares will be CA64128F7039.

No fractional Common Shares will be issued as a result of the Share Consolidation. Any fractional interest in Common Shares that would otherwise result from the Share Consolidation will be rounded up to the next whole Common Share, if the fractional interest is equal to or greater than one-half of a Common Share, and rounded down to the next whole Common Share if the fractional interest is less than one-half of a Common Share. In all other respects, the post-consolidation Common Shares will have the same attributes as the pre-consolidation Common Shares.

Common Share purchase warrants issued by the Company in connection with the Company’s July 2020 public offering of units (the “July Warrants”) and the Company’s January 2021 public offering of units (the “January Warrants”), respectively, are listed for trading on the TSX. As a result of the Share Consolidation (i) the July Warrants will be adjusted in accordance with the terms of the warrant indenture dated July 28, 2020 such that ten July Warrants will now be exercisable for one post-consolidation Common Share following the payment of an adjusted exercise price of C$2.00, and (ii) the January Warrants will be adjusted in accordance with the terms of the warrant indenture dated January 29, 2021 such that ten January Warrants will now be exercisable for one post-consolidation Common Share following the payment of an adjusted exercise price of C$2.20.

The Company’s transfer agent, Computershare Investor Services Inc. (“Computershare”), will act as the exchange agent for the Share Consolidation. Letters of transmittal were mailed to registered shareholders in connection with the Meeting and a copy is available on www.sedar.com. Registered shareholders are requested to submit their share certificates, or DRS advices, as applicable, together with their completed letters of transmittal, to Computershare. Until surrendered, each share certificate (or DRS advice) representing pre-consolidation Common Shares will be deemed to represent the number of whole post-consolidation Common Shares to which the shareholder is entitled as a result of the Share Consolidation.

Beneficial shareholders who hold their Common Shares through intermediaries (securities brokers, dealers, banks, financial institutions, etc.) and who have questions regarding how the Share Consolidation will be processed should contact their intermediaries.

About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.
www.nevadacopper.com
Mike Brown, Interim President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to the timing and completion of the Share Consolidation.

Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of its underground mine (the “Underground Mine”) within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; failure to obtain extensions under and amendments to the Company’s amended and restated senior credit facility with KfW IPEX-Bank; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements and information. The forward-looking information and statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.

Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Categories
Base Metals Energy Junior Mining Nevada Copper

Nevada Copper Provides Operations and Financing Updates

YERINGTON, Nev., Aug. 31, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF) (“Nevada Copper” or the “Company”) today provided an update regarding operations at the underground mine at its Pumpkin Hollow project (the “Underground Mine”), as well as an update on financing matters. All amounts below are stated in US dollars.

Operations Update

  • Stoping and Lateral Development: Development and penetration through the water bearing dike has now been completed on the first crossing. Lateral development beyond this crossing is now into solid ground at a pace consistent with mine plan rates focused on establishing production from the East-North deposit. In addition, with steel support beams recently installed, a second crossing is expected in the coming weeks, further enhancing development rates.
  • Stoping: The Company has mined the second stope in the Alphabet Zone at a CuEq grade of 1.45% with backfilling scheduled to start in the coming week.
  • Surface Ventilation Fans: Delivery of the surface fans remains on schedule with installation and commissioning expected to be completed in Q4 2021 with sustainable hoisting rates of 3,000 tpd expected to follow.

We are pleased to have completed our first crossing of the water dike enabling our development rates to increase in line with our mine plan expectations,” stated Mike Brown, Interim Chief Executive Officer of Nevada Copper. “We look forward to continued production rate increases in Q3 and Q4 of this year.”

Financing Update

  • KfW Credit Facility Amendment Discussions: On August 31, 2021, the Company received an extension of the waiver from KfW IPEX-Bank (“KfW”), the Company’s senior project lender, to September 30, 2021 to complete the project completion test (the “Project Longstop Date”) under the amended and restated credit agreement (“Amended KfW Facility”). The Company is in discussions with KfW regarding a longer-term extension of the Project Longstop Date into 2023; deferral of debt servicing by up to twenty-four months; and the deferral of certain financial covenants under the Amended KfW Facility to further support the ramp-up of the Underground Mine. The Company expects to have the proposed extension and amendments finalized in the next month. However, there can be no assurance that such extension and amendments will be finalized by such times or at all. Failure to finalize the extension would result in the Company being in default under the Amended KfW Facility.
  • Additional $13M of liquidity: The existing Promissory Note provided by Pala Investments Limited, the Company’s largest shareholder (“2021 Promissory Note”) has been amended (subject to regulatory approval) to allow total borrowings of up to $55 million, providing an additional $13 million of liquidity to the Company. Further draws by the Company are subject to agreed use of proceeds. The 2021 Promissory Note has a maturity date of June 30, 2022, and bears interest at 8% per annum on amounts drawn. Pursuant to the amendment, the 2021 Promissory Note now provides for an arrangement fee of 6% on the full commitment amount of $55 million, which will be capitalized. The proceeds will be used to fund the development and ramp-up of the Underground Mine and related working capital needs. The amendment was reviewed and approved by a committee of independent directors of the Company.

Qualified Persons
The technical information and data in this news release was reviewed by Greg French, C.P.G., and Norm Bisson, P.Eng., for Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.

About Nevada Copper
Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.
www.nevadacopper.com
Mike Brown, Interim President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to mine development plans, production and ramp-up plans, equipment installation, requested amendments to the Amended KfW Credit Facility, and regulatory approval of the 2021 Promissory Note.

Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; failure to obtain extensions under and amendments to the Amended KfW Facility; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements and information. The forward-looking statements and information contained herein are based upon assumptions management believes to be reasonable, including, without limitation: no adverse development in respect of the property at the Pumpkin Hollow project; no material changes to applicable laws; the ramp-up of operations at the Underground Mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of the COVID-19 pandemic in the medium-term and long-term; no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended. The forward-looking information and statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.

Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Categories
Base Metals Energy Junior Mining Nevada Copper

Nevada Copper Announces Filing of Q2 2021 Financial Statements and MD&A, Operational Update and Management Change

YERINGTON, Nev., Aug. 13, 2021 (GLOBE NEWSWIRE) — Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF) (“Nevada Copper” or the “Company”) today provided an operations update and announced filing of its Q2 2021 financial statements and the related management’s discussion and analysis.

Operations Update

  • Mining of First Stope: During Q2 2021 the Company successfully mined approximately 9,500 tons at a grade of 1.5% Cu out of the first stope mined since the restart of the mine in the East South area. Tons mined and ore breakage was consistent with the plan, indicating that the mining method was appropriate for the ground conditions where the stope is located, although mining of the stope was later than originally planned. Subsequently, the stope was successfully back-filled and the Company is now preparing to mine the next stope in the East South area.
  • Mine Infrastructure: Mine infrastructure works were further advanced during the quarter albeit slower than expected, including the final two sets of underground fans installed and commissioned as planned in Q2 2021, allowing for an increase in development rates. Commissioning of the surface ventilation fans continues to be planned for Q4 2021.
  • Material Hoisting: Following completion of the Main Shaft material handling system in Q4 2020, the Underground Mine achieved a peak daily hoisting rate of over 3,000 tons by February 2021 and has since achieved a hoisting rate equivalent to 5,000 tons per day (“tpd”) on a shift basis, demonstrating capacity of the shaft and associated materials handling system. Due to slower development rates in Q2 2021 through the water-bearing dike structure, the Company now expects to reach sustainable hoisting rates of 3,000 tpd in Q4 2021 and for hoisting rates to continue to ramp-up beyond that.
  • Lateral Development: Lateral development continued on multiple headings, providing access to ore mining zones in the East South orebody and advancing development towards the East North orebody. During the Q2 2021 the Company continued development of the East North area through a dike structure located between the East South and East North orebodies. A second heading crossing the dike is 90 feet below the first heading. Additional ground support was required to complete dike crossing and the Company is almost through the water-bearing dike structure.
  • Processing: The process plant maintained average concentrate grade over 21% along with 81% recoveries. While batch processing ore through the processing plant, the Company achieved a weekly average of 3,271 tpd. 87,211 tons of ore was processed through the concentrator in Q2 2021 with an average feed grade of 0.51%. Approximately 1,514 tons of concentrate was produced at a 21% average copper grade for Q2 2021. During June, Sedgman successfully completed C5 testing of the processing plant for grind size and moisture of concentrate and tailings.
  • Production ramp-up and Mine Planning: The Company continues to advance its mine planning process and has made revisions to the mine plan. The revised mine plan incorporates the recent experiences during mine development, including the geotechnical conditions of the East South area. In light of the impact of the water-bearing dike structure, expected equipment utilization rates and the remaining infrastructure projects to be completed the Company now expects that the Underground Mine will reach a hoisting rate of 3,000 tpd in Q4 2021 and 5,000 tpd in H1 2022.

Property Development Plans

  • Underground: The Company has progressed its life-of-mine planning aimed at operating its underground mine at an ultimate production rate in excess of the originally contemplated 5,000 tons per day rate. Mine planning work further supports the potential for the mine, once ramped-up to steady-state, to operate at higher long-term rates of 6,500 tons per day milled, increasing long-term annual copper production potential.
  • Open Pit: The Company reviewed its longer-term development targets for its Pumpkin Hollow property, including a solar power study, electrification and emissions reduction analysis, follow up work on scaling opportunities to improve economics and plans for infill and extension drilling.
  • Exploration: The Company plans to follow up on new exploration targets added through recent expansion of the Company’s properties to the east and analysis of geophysical surveys.

Corporate

  • Payroll Protection Program Loan (“PPP Loan”) Forgiveness: on August 6, 2021, the Company received confirmation for the approval of the forgiveness of the PPP Loan in the amount of $2.4 million. The loan was received in 2020 as part of a United States government COVID-19 pandemic program to assist companies to retain their employees.
  • KfW Credit Facility Amendment Discussions: On June 30, 2021, the Company received a waiver from KfW IPEX-Bank (“KfW”), the lender under its amended and restated senior credit agreement (the “Amended KfW Facility”), which provided for a 60-day extension to the project completion longstop date (the final date to meet the requirements of the project completion test under the Amended KfW Facility) (the “Project Longstop Date”) from June 30, 2021 to August 31, 2021. The Company has requested and expects to receive a further short-term extension of the Project Longstop Date from KfW. The Company is also in discussions with KfW to achieve a longer-term extension of the Project Longstop Date to a date in 2023, the deferral of debt servicing by twelve months and the temporary deferral of compliance with certain financial covenants under the Amended KfW Facility as the Underground Mine continues to ramp-up. The Company expects to have the short-term extension finalized in the next few weeks and the other proposed amendments finalized in the next few months. However, there can be no assurance that such extension and amendments will be finalized by such times or at all. Failure to finalize the extension or these amendments would result in the Company being in default under the Amended KfW Facility.
  • 2021 Promissory Notes: The Company received a loan of $15 million under a promissory note with Pala Investments Limited (“Pala”), the Company’s largest shareholder, in June 2021 (the “2021 Promissory Note”) providing additional liquidity for the ramp-up of the Underground Mine and addressing the reduced development rates associated with crossing the water-bearing dike structure. The 2021 Promissory Note has a maturity date of June 30, 2022, and bears interest at 8% per annum on amounts drawn. Subsequent to the end of Q2 2021, Pala agreed to provide the Company with additional loans of up to $27 million (of which $19 million has been received) pursuant to a series of amendments and restatements of the 2021 Promissory Note (the “Amended and Restated Promissory Note”) on the same terms and conditions as the original 2021 Promissory Note. Further draws by the Company are subject to agreed use of proceeds and regulatory approval of the Amended and Restated Promissory Note.
  • 2021 Credit Facility: On February 3, 2021, the Company entered a credit facility with Pala, for $15 million to be drawn by the Company (the “2021 Credit Facility”). The 2021 Credit Facility also provided $15 million under an accordion feature. The full $30 million has been drawn by the Company.

Senior Management Changes

Mike Ciricillo will be stepping down from the role of President and Chief Executive Officer of the Company, effective August 14, 2021.

Mike Brown will assume the role of Interim President and Chief Executive Officer. Mr. Brown has been a non-executive director of Nevada Copper since 2013 and has over 35 years of underground and open pit mining experience, including as Chief Operating Officer of De Beers Consolidated Ltd., where he was responsible for five operating mines. Mr. Brown has also managed a number of major projects, including the $750 million Finsch block 4 project, the $1.3 billion Venetia underground feasibility study, and a $200 million construction and commissioning of the Voorspoed mine.

Mr. Ciricillo will continue to provide support at the Pumpkin Hollow site for a transition period.

“The board of directors would like to thank Mr. Ciricillo for his contributions to the Company, including execution on ramp-up of the Underground Mine, and look forward to his ongoing support,” stated Chairman Mr. Gill. “The board of directors is pleased to welcome Mr. Brown as interim President and CEO and look forward to his leadership in that role.”

Q2 2021 Financial Statements

The Company has filed on SEDAR its condensed interim financial statements and the related management’s discussion and analysis for the quarter ended June 30, 2021. These documents are available on the Company’s website at www.nevadacopper.com and the Company’s SEDAR profile at www.sedar.com.

Qualified Persons

The technical information and data in this news release was reviewed by Greg French, C.P.G., and Norm Bisson, P.Eng., for Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.

About Nevada Copper

Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade underground mine and processing facility, which is now in the production stage, and a large-scale open pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.
www.nevadacopper.com

Mike Ciricillo, President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information and forward-looking statements within the meaning of applicable Canadian and United States securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to statements and information that relate to: Nevada Copper’s plans for the Project; negotiations with KfW regarding amendments to the Amended KfW Facility and waivers thereunder; the Company’s mine development, production and ramp-up plans and the expected timing, costs and results thereof; the need for additional funding; the resolution of hydrogeological issues; the impacts of the COVID-19 pandemic on the global economy and the Company; future ore and concentrate production rates; expected commencement of positive cash flow from operating activities; the ongoing exploration activities and the objectives and results thereof; and the other plans of Nevada Copper with respect to the exploration, development, construction and commercial production at the Underground Mine.

Forward-looking statements and information include statements regarding the expectations and beliefs of management. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information should not be read as guarantees of future performance and results. They are subject to known and unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Such risks and uncertainties include, without limitation, those relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of the COVID-19 pandemic on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues and penetrate the dike at the Underground Mine; failure to obtain extensions under and amendments to the Amended KfW Facility; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labour disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry, as well as those risks discussed in the Company’s Management Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements and information. The forward-looking statements and information contained herein are based upon assumptions management believes to be reasonable, including, without limitation: no adverse development in respect of the property at the Project; no material changes to applicable laws; the ramp-up of operations at the Underground Mine in accordance with management’s plans and expectations; no worsening of the current COVID-19 related work restrictions; reduced impacts of the COVID-19 pandemic in the medium-term and long-term; no material adverse change to the price of copper from current levels; and the absence of any other factors that could cause actions, events or results to differ from those anticipated, estimated or intended. The forward-looking information and statements are stated as of the date hereof. Nevada Copper disclaims any intent or obligation to update forward-looking statements or information except as required by law. Readers are referred to the additional information regarding Nevada Copper’s business contained in Nevada Copper’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in forward-looking statements, there may be other factors that could cause actions, events or results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s filings that are available at www.sedar.com.

Nevada Copper provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Categories
Base Metals Energy Junior Mining Nevada Copper

Nevada Copper Announces Further Progress with Underground Operations and Strategic Project Development

July 12, 2021View PDF

Yerington, NV – July 12, 2021 – Nevada Copper Corp. (TSX: NCU) (OTC: NEVDF) (“Nevada Copper” or the “Company”) is pleased to provide an update regarding the ramp-up of the Underground Mine and development activities for the Open Pit project at its 100%-owned, fully-permitted Pumpkin Hollow Project in Nevada.

Production Ramp-Up Update

  • Safe and effective penetration of dike structure: The Company is in the process of safely completing the dike crossing. As reported on May 17, 2021, ground and hydrological conditions associated with the dike reduced development rates for a temporary period while traversing the dike to allow for grouting and ground control. With the completion of the dike crossing within the next two weeks, the Company expects to see lateral development rates increase back to planned rates this month.
  • Underground ventilation commissioned on-schedule: All underground ventilation fans were installed and commissioned during May, as planned. The final surface fans continue to be planned for delivery in Q3 2021 and commissioning in Q4 2021. Consequently, achievement of steady-state production continues to be expected in Q4 2021.
  • Successful completion of process plant C5 Testing: During June, Sedgman successfully completed C5 testing of the processing plant for grind size and moisture.

Mike Ciricillo, Nevada Copper’s Chief Executive Officer, stated:

“I am pleased with the continued progress with the ramp-up from Pumpkin Hollow. The safe penetration of the dike and commissioning of the underground ventilation system are significant de-risking steps and facilitate increasing development and production rates, as we progress to steady-state. The longer-term mine planning work being advanced indicates future potential upside for both Underground and Open Pit projects.”

Project Development

  • Underground Mine Planning supports potential for higher long-term production rates: As part of its project development objectives reported on March 1, 2021, the Company has progressed its life-of-mine planning aimed at operating its underground mine at an ultimate production rate in excess of the originally contemplated 5,000 tons per day rate. Mine planning work during Q2 2021 further supports the potential for the mine, once ramped-up to steady-state, to operate at higher long-term rates of 6,500 tons per day milled, increasing long-term annual copper production. This additional production capacity would also support accelerated mining of the significant additional underground copper resources that exist over and above the current underground reserve. Further engineering work will be undertaken during H2 2021 to support the potential for a higher long-term production rate from the underground operation.
  • Open Pit Solar Power Study indicates potential to further reduce Open Pit power costs: The Company has also progressed the planned feasibility studies for a potential solar project, with renewables consulting group Sprout Associates, with the following initial conclusions. Further updates will be provided upon completion of the next phase of study work:
    • Pumpkin Hollow benefits from ample sun and land to support a large solar project with the capacity to meet a significant portion of the Open Pit project’s power requirements;
    • The solar potential at the site is up to 200MW;
    • Already low grid power costs in Nevada could be materially further reduced through an on-site solar plant; and
    • A third-party solar project provides an option to remove upfront power infrastructure costs from the Open Pit project.

Balance Sheet Update

  • Further to the Company’s announcement on May 17, 2021, Pala Investments Limited has agreed to provide additional financing of US$25 million through a promissory note (in addition to the fully drawn existing US$30 million credit facility), providing additional liquidity for the ramp-up and addressing the reduced development rates associated with the dike grouting program. The Company has drawn US$15 million under the promissory note, with subsequent draws available at the Company’s option, subject to agreed use of proceeds. The promissory note has a maturity date of June 30, 2022 and bears interest at 8% per annum on amounts drawn. The promissory note was reviewed and approved by the independent members of the Company’s board of directors. In addition, US$9 million remains available to draw under the Company’s working capital facility with its offtake partner, Concord Resources Limited.
  • The Company has received proceeds of CAD$1.4 million for exercise of warrants so far in 2021. The Company has the potential to receive a further CAD$65 million of warrant proceeds should all the outstanding warrants expiring in January 2022 with an exercise price of CAD$0.20 (the “January 2022 Warrants”) be exercised prior to maturity. In addition to the January 2022 Warrants, a further CAD$34 million of warrant exercise proceeds may be received should the outstanding warrants expiring in July 2022 with an exercise price of CAD$0.22 be exercised in full prior to maturity.
  • The Company’s senior lender, KfW IPEX-Bank (“KfW”), has provided the Company with a 60-day extension to the project completion longstop date from June 30, 2021 to August 31, 2021, while the parties agree on a revised completion test and longstop date for the project. The Company will provide a further update once a revised project completion test and longstop date has been agreed with KfW. While the Company expects to agree on an appropriate revised date with KfW, there can be no assurance this will be achieved.
  • The Company continues to undertake near-term mine planning to incorporate the recent impact of the dike on development rates and other factors that have slowed the production ramp-up. It is possible that such mine plan updates may indicate higher operating costs and additional development capital and working capital requirements for the ramp-up than previously contemplated.

Qualified Persons

The information and data in this news release was reviewed by Greg French, C.P.G., and Norm Bisson, P.Eng., for Nevada Copper, who are non-independent Qualified Persons within the meaning of NI 43-101.

About Nevada Copper

Nevada Copper (TSX: NCU) is a copper producer and owner of the Pumpkin Hollow copper project. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully permitted projects include the high-grade Underground Mine and processing facility, which is now in the production stage, and a large-scale Open Pit project, which is advancing towards feasibility status.

NEVADA COPPER CORP.

www.nevadacopper.com

Mike Ciricillo, President and CEO

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179

Cautionary Language

This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to mine development plans, production and ramp-up plans and the expected timing and results thereof, equipment installation, and further discussions with KfW.

Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information are subject to known or unknown risks, uncertainties and other factors which may cause the actual results and events to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Forward-looking statements or information are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements or information, including, without limitation, risks and uncertainties relating to: the ability of the Company to complete the ramp-up of the Underground Mine within the expected cost estimates and timeframe; requirements for additional capital and no assurance can be given regarding the availability thereof; the impact of COVID-19 on the business and operations of the Company; the state of financial markets; history of losses; dilution; adverse events relating to milling operations, construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, construction and ramp-up of the Underground Mine; loss of material properties; interest rates increase; global economy; limited history of production; future metals price fluctuations; speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates from management’s expectations and the difference may be material; legal and regulatory proceedings and community actions; accidents; title matters; regulatory approvals and restrictions; increased costs and physical risks relating to climate change, including extreme weather events, and new or revised regulations relating to climate change; permitting and licensing; volatility of the market price of the Company’s securities; insurance; competition; hedging activities; currency fluctuations; loss of key employees; other risks of the mining industry as well as those risks discussed in the Company’s Management’s Discussion and Analysis in respect of the year ended December 31, 2020 and in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 18, 2021. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. The forward-looking information and statements are stated as of the date hereof. The Company disclaims any intent or obligation to update forward-looking statements or information except as required by law.

The Company provides no assurance that forward-looking statements and information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements and information.