Nevada Copper Announces Further Ramp-up Progress & Closing of Credit Facility Increase


Press Release


Corporate Presentation

Nevada Copper CEO Mike Ciricillo comments, “The team continues to improve the performance both at the mine and processing plant, evidenced by the operational metrics for December. Most importantly, they have done it safely. In addition, the commissioning of the main hoist system is progressing well, with the shaft reaching its full production speed further enabling the ramp-up to our goal of 5,000 tpd of hoisted material. We are well on our way to show the potential of the Pumpkin Hollow Underground Project.”

For further information contact:
Rich Matthews, Investor Relations
Integrous Communications
rmatthews@integcom.us
+1 604 757 7179